Specifications
Power Entry Control Module – Direct Current (PECM-DC), Continued
The following procedure should be used for replacement of the PECM-
DC in the Maxum II Modular Oven configuration.
PECM-DC
Removal and
Installation
Step Procedure
1. Turn off power to the Maxum II at the main circuit breaker.
2. Open electronic enclosure door (using a 4mm (5/32”) Allen
wrench if necessary).
3. Remove all other cables connected to PECM-DC. These
include 24V input power, CIM power, purge control, oven
power, oven heater control, solenoids, and I
2
C cables. Label
each cable with its connection location as it is removed.
4. Unplug the atmospheric reference tube from the purge
switch. (Tubing connection on the bottom right side of the
PECM-DC). Refer to Figure 4-2.
5. Remove the 8 screws that secure the board to the EC, and
remove the board. Note that solenoid tubes run behind the
PECM-DC board. These should remain in the same location
with the new board.
6. On the replacement PECM-DC verify that the Purge Disable
jumper JP2 is set to match the board that was removed.
7. Install the replacement PECM-DC using the 8 screws.
8. Reattach the atmospheric reference tube from the purge
switch (tubing connection on the bottom right side of the
PECM-DC).
9. Reattach all cables to the PECM-DC. Make sure that plug
in locations and labels match. Refer to Figure 4-2.
10. After verifying all connections are correct, apply power to
the analyzer.