User manual
Dependencies 5-3
If the February 8th symbol is moved to the right, the
triangle symbol will move an equal amount. The 2/3
symbol will not move because it is to the left of the 2/8
symbol. Thus, the 2/8 symbol is the parent symbol, and
the 2/15 symbol is dependent on its movement. The
vertically linked symbols are also dependent symbols.
Here, the 2/8 symbol is moved 10 days to the right, as
shown in the tooltip box that appears as the symbol is
moved.
All symbols linked to the parent symbol and to the right of
the parent symbol on the same task row are dependent
and should move an equal amount.
All dependent symbols have shifted 10 working days,
matching the movement of the parent symbol. The 2/3
symbol remained in place because it is to the left of the
parent symbol.
Move dependent symbols based on duration
By default, when moving a symbol (predecessor), that symbol’s dependent symbols (successors) may be moved to
a date outside the workday time period or to a non-working day.
By checking Always move dependent symbols based upon duration as found under Tools | Program Options
| Dates, the dependent tasks will move the amount of working time the parent symbol was moved. This prevents
tasks from being pushed into non-working times and ensures duration values remain constant for the dependent
tasks.
Example:
In this example, the task begins on Monday and ends on Friday. The
weekends are shaded and are non-working days.
With Always move dependent
symbols based upon duration, moving
the start date forward by one day
would result in the end date moving
ahead one day, to the next working
day, as shown to the left. The duration
would remain as fi ve days.