7.1 Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure See
1. Commission the inverter. see section7.2, page56
2. Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
Direct connection via WLAN
Direct connection via Ethernet
Connection via WLAN in the local network
Connection via Ethernet in the local network
see section7.3, page58
3. Log into the user interface. see section7.4, page62
4. Select the inverter configuration option. Please note that
the SMAGridGuard code for changing the grid-relevant
parameters must be available after completion of the first
ten feed-in hours or installation assistant (see "Application
for the SMAGridGuard code" available at www.SMA-
Solar.com).
see section7.5, page63
5. Ensure that the country data set has been configured cor-
rectly.
Inverter user manual
6. Make further inverter settings as needed. Inverter user manual
7.2 Commissioning the Inverter
WARNING
Danger to life due to fire or explosion when batteries are fully discharged
A fire may occur due to incorrect charging of fully discharged batteries. This can result in death
or serious injury.
Before commissioning the system, verify that the battery is not fully discharged.
Do not commission the system if the battery is fully discharged.
If the battery is fully discharged, contact the battery manufacturer for further proceedings.