7 Commissioning
7.1 Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure See
1. Commission the inverter. see section7.2, page41
2. Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
Direct connection via WLAN
Connection via WLAN in the local network
Connection via Ethernet in the local network
see section7.3, page43
3. Log into the user interface. see section7.4, page47
4. Select the inverter configuration option. Please note that
the SMAGridGuard code for changing the grid-relevant
parameters must be available after completion of the first
ten feed-in hours or installation assistant (see "Application
for the SMAGridGuard code" available at www.SMA-
Solar.com).
see section7.5, page48
5. If necessary, set the parameters for voltage and frequency
monitoring.
see section7.6, page50
6. Ensure that the country data set has been configured cor-
rectly.
Inverter user manual
7. Make further inverter settings as needed. Inverter user manual
7.2 Commissioning the Inverter
Requirements:
A means of disconnecting the inverter from the PV array must be present.
The AC circuit breaker must be correctly rated and mounted.
The inverter must be correctly mounted.
All conductors must be correctly connected.
Unused enclosure openings must be sealed tightly with sealing plugs.