6.3 Managing Small-Scale PV Plants with Sunny Explorer
6.3.1 Functions and Parameter Settings in Sunny Explorer
The following functions for small-scale PV plant management in Sunny Explorer are available:
Overview of the status of the small-scale PV plant
Graphic display of key plant data, device data and energy values
Parameterization of individual devices or an entire device class
Simple diagnostics thanks to display of faults and events
Data export of inverter energy values and events in CSV format
Piggy-Back update
You can change the following parameters in Sunny Explorer:
Device name of the inverter
Automatic IP configuration On/Off
DNS-IP, gateway IP, IP address, subnet mask
Webconnect function On/Off
6.3.2 Creating a Small-Scale PV Plant in Sunny Explorer
Requirements:
The small-scale PV plant must be commissioned (see Section6.2, page31).
The inverter with Piggy-Back must be in feed-in operation.
Sunny Explorer must be installed on the computer (see Section2.5 "Supported Products",
page13).
Procedure:
1. Connect the computer to the router/network switch of the small-scale PV plant using a network
cable.
2. If you have used the SMA Connection Assist for the static network configuration, ensure that the
SMA Connection Assist has ended.
3. Start Sunny Explorer and create a Speedwire plant for the small-scale PV plant in
Sunny Explorer (see Sunny Explorer help).