Installation step by step
Although the transformer is designed to withstand inclement weather,
you are recommended not to place it close to a sprayer system. Place
the transformer at least 50 cm above the ground and in the immediate
vicinity of a 110V/230V electric socket.
Installing the transformer (Fig. 5)
Step 1
Open the package of the transformer. Here you will find the screws for
fixing the transformer in place and the terminal lugs for the cable. Fix the
transformer to a wall, panel or post using the screws supplied (Fig. 1).
Step 2
Split about 5-10 cm of the low-voltage cable end into 2 wires. Remove about 8
mm of insulation from both wire ends (Fig. 2).
Step 3
Remove the lid from the transformer so you get access to the 3 cable terminals.
Each terminal represents a separate light section in your garden.
Step 4
Insert the copper wires into the terminal lug (Fig. 3) and fix them firmly in place
by pressing the click mechanism down (Fig. 4).
Step 5
Put the lid back in place on the transformer to cover the cable terminals.(Fig. 5).
Step 6
Put the plug of the 110V/230V power cable into the electric socket. The
transformer will be switched on automatically. The on-off button on the side of
the transformer will light up continuously. (At any time it is possible to switch the
transformer on and off by a push on the on/off button)