Ultra Rail Installation Manual
snapnrack.com
24
Ultra Rail Splice
INSTALLATION INSTRUCTIONS
1/8"
1) Align sections of rail so that ends
butt up to each other.
2) Install rail splice assembly onto
bottom of rail, making sure both
rails are seated in grooves of splice
and that the splice is centered.
3) Tighten splice hardware.
Hold sides of splice together on rails
with one hand and tighten with the
other.
Best Practice:
Leave approximately 1/8” gap
between rails to allow for thermal
expansion of rail.
Any section of rail that is spliced
will need to be supported by a roof
attachment on both sides. Splices
are not allowed to be installed on rail
cantilevers.
Install Note:
Gap between rails must land between
bonding clips on splice.
Install Note:
D
.125
1/8" - 1/4" RAIL GAP
2" MAX
2" MAX
RAIL EDGE MUST NOT
PASS CLIP EDGE, AS SHOWN
Splice Installation Limitations