SA-15K Install Guide and Owner Manual
August 19
th
, 2022 19
Physical Installation
Inverter Components
A. LCD Touch Screen G. 200A Load Breaker
B. PV Disconnect Switch H. Sensor Input Board
C. ON/OFF Button I. Battery Terminal Blocks (+ + || - -)
D. WI-FI Dongle Input J. MPPT Inputs
E. 2 x 200A Battery Breaker K. Neutral/Ground Bus Bar
F. Communication Ports L. Terminal Blocks (GEN/ Load/ Grid)
Deciding Backup Circuits
A. Ensure you keep the inverter within its amperage limits
• ON-Grid = 200A Continuous (pass-through)
• OFF-Grid = 12kW = 50A Continuous (62.5A w/ solar) | 24kW = 100A Peak (10s) | 30kW = 125A Peak (100ms)
B. Verify each load circuit by measuring typical and max Amps with a clip-on Amp meter. Amps x 120V = Watts
C. Install a subpanel for backup loads if there is a chance of exceeding any amperage limits while powering the
entire home off-grid, failure to do so will result in outage and potential damage to the inverter (see pg. 12).
D. If you have Arc-Fault / GFI breakers, DO NOT use a multi-circuit transfer switch.
A
B
C
D
E
G
F
I
J
K
L
H