Three Phase System With SetApp Configuration Installation Guide For North America Version 1.
Disclaimers Disclaimers Important Notice Copyright © SolarEdge Inc. All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted, in any form or by any means, electronic, mechanical, photographic, magnetic or otherwise, without the prior written permission of SolarEdge Inc. The material furnished in this document is believed to be accurate and reliable. However, SolarEdge assumes no responsibility for the use of this material.
Support and Contact Information Support and Contact Information If you have technical problems concerning SolarEdge products, please contact us: l USA and Canada: 1 510 498 3200 l Worldwide: +972 073 2403118 l Fax: +1 (530) 273-2769 l Email: ussupport@solaredge.com. l Support Center: https://www.solaredge.com/us/service/support Before contact, make sure to have the following information at hand: l Model and serial number of the product in question.
Revision History Revision History Version 1.1 (Dec. 2018) l Updated communication options and menus l Updated guidelines for use of extension cables in power optimizer installation Version 1.0 (Sept. 2018) Initial release -Three Phase System Installation Guide MAN-01-00527-1.
Contents Contents Disclaimers 1 Important Notice 1 FCC Compliance 1 Support and Contact Information 2 Revision History 3 Version 1.1 (Dec. 2018) 3 Version 1.0 (Sept.
Contents Power Control Device Manager Maintenance Information Step 3: Verifying Proper Activation and Commissioning Viewing System Status Main Inverter Status Site Status Communication Status Inverter Energy Status Meter Status Reporting and Monitoring Installation Data The Monitoring Platform Creating Logical and Physical Layout using Installation Information Designer Mapper Application Physical Layout Editor Using a Paper Template Chapter 6: Setting Up Communication Communication Options Ethernet RS485 Ce
Contents Adding, Removing, or Replacing Power Optimizers Technical Specifications - Three Phase Inverters (North America) Default Trip Limits and Times According to IEEE1547 Safety Switch 6 71 72 74 74 -Three Phase System Installation Guide MAN-01-00527-1.
HANDLING AND SAFETY INSTRUCTIONS HANDLING AND SAFETY INSTRUCTIONS During installation, testing and inspection, adherence to all the handling and safety instructions is mandatory. Failure to do so may result in injury or loss of life and damage to the equipment. Safety Symbols Information The following safety symbols are used in this document. Familiarize yourself with the symbols and their meaning before installing or operating the system. WARNING! Denotes a hazard.
IMPORTANT SAFETY INSTRUCTIONS IMPORTANT SAFETY INSTRUCTIONS SAVE THESE INSTRUCTIONS CONSIGNES DE SÉCURITÉ IMPORTANTES CONSERVEZ CES INSTRUCTIONS WARNING! The inverter cover must be opened only after switching the inverter ON/OFF/P switch located at the bottom of the inverter to OFF. This disables the DC voltage inside the inverter. Wait five minutes before opening the cover. Otherwise, there is a risk of electric shock from energy stored in the capacitors.
IMPORTANT SAFETY INSTRUCTIONS WARNING! The inverter input and output circuits are isolated from the enclosure. This system does not include an isolation transformer and should be installed with an ungrounded PV array in accordance with the requirements of NEC Articles 690.35 and 690.43 National Electric Code, ANSI/NFPA 70, 2011 (and Canadian Electrical Code, Part I, for installations in Canada).
IMPORTANT SAFETY INSTRUCTIONS NOTE The symbol appears at grounding points on the SolarEdge equipment. This symbol is also used in this manual. NOTE A SolarEdge inverter may be installed in a site with a generator, however must not operate at the same time as the generator. Operating an inverter and a generator simultaneously will void the warranty. SolarEdge requires installing a physical or electronic interlock, which will prevent the generator and inverter from operating simultaneously.
Chapter 1: Introducing the SolarEdge Power Harvesting System Chapter 1: Introducing the SolarEdge Power Harvesting System The SolarEdge power harvesting solution maximizes the power output from any type of solar Photovoltaic (PV) installation while reducing the average cost per watt. The following sections describe each of the system’s components.
Inverter with Safety Switch Each power optimizer also transmits module performance data over the DC power line to the inverter. Two types of power optimizers are available: l Module Add-on power optimizer – connected to one or more modules l Smart modules - the power optimizer is embedded into a module Inverter with Safety Switch The inverter efficiently converts DC power from the modules into AC power that can be fed into the main AC service of the site and from there to the grid.
Chapter 1: Introducing the SolarEdge Power Harvesting System Installation Procedure The following is the procedure for installing and setting up a new SolarEdge site. Many of these also apply to modification of an existing site. 1. Connecting Power Optimizers in Strings, page 21. 2. Recording power optimizer serial numbers (optional), page 49. 3. Mounting the inverter, Page 28. 4. Connecting the strings and the AC to the Safety Switch, page 33. 5. Commissioning and activating the installation, page 41. 6.
Chapter 2: Installing the Power Optimisers Chapter 2: Installing the Power Optimisers Safety The following notes and warnings apply when installing the power optimizers. Some of the following may not be applicable to smart modules: WARNING! The metallic enclosure of the power optimizer must be grounded in accordance with the product's listing and local and national codes.
Chapter 2: Installing the Power Optimisers CAUTION! If you intend to mount the optimizers directly to the module or module frame, first consult the module manufacturer for guidance regarding the mounting location and the impact, if any, on module warranty. Drilling holes in the module frame should be done according to the module manufacturer instructions.
Installation Guidelines Installation Guidelines l l l l l l Frame-mounted power optimizers are mounted directly on the module frame , regardless of racking system (rail-less or with rails). For installation of frame-mounted power optimizers, refer to http://www.solaredge.com/sites/default/files/installing_ frame_mounted_power_optimizers.pdf. The steps in this chapter refer to module add-on power optimizers.
Chapter 2: Installing the Power Optimisers Figure 3: Power optimizer clearance l When installing modules in a confined space, for example, if installing Building-integrated photovoltaic (BIPV) modules, ventilation measures may be needed to ensure the power optimizers are not be exposed to temperatures outside their specifications. NOTE The images contained herein are for illustrative purposes only and may vary depending on product models. -Three Phase System Installation Guide MAN-01-00527-1.
Step 1: Mounting and Grounding the Power Optimizers Step 1: Mounting and Grounding the Power Optimizers For each of the power optimizers1: 1. Determine the power optimizer mounting location and use the power optimizer mounting brackets to attach the power optimizer to the support structure (See Figure 4). It is recommended to mount the power optimizer in a location protected from direct sunlight.
Chapter 2: Installing the Power Optimisers Figure 4: Power optimizer installation and grounding using a star washer l For mounting on rails with sliding nut fasteners: If the star washer cannot be used, use the SolarEdge grounding plate (purchased separately) between the railing and the flat side of the mounting bracket. Use mounting specific hardware as needed. Apply torque of 9.5 N*m / 7 lb*ft.
Step 2: Connecting a PV Module to a Power Optimiser 6. Record power optimizer serial numbers and locations, as described in Reporting and Monitoring Installation Data on page 49. Step 2: Connecting a PV Module to a Power Optimiser NOTE Images are for illustration purposes only. Refer to the label on the product to identify the plus and minus input and output connectors.
Chapter 2: Installing the Power Optimisers Step 3: Connecting Power Optimizers in Strings You can construct parallel strings of unequal length, that is, the number of power optimizers in each string does not have to be the same. The minimum and maximum string lengths are specified in the power optimizer datasheets. Refer to the Designer for string length verification. IMPORTANT SAFETY FEATURE For a compliant PV Rapid Shutdown System (PVRSS) installation, use no more than 30 optimizers per string. 1.
Step 4: Verifying Proper Power Optimiser Connection Step 4: Verifying Proper Power Optimiser Connection When a module is connected to a power optimizer, the power optimizer outputs a safe voltage of 1V (±0.1V). Therefore, the total string voltage should equal 1V times the number of power optimizers connected in series in the string. For example, if 10 power optimizers are connected in a string, then 10V should be produced. Make sure the PV modules are exposed to sunlight during this process.
Chapter 3: Installing the Inverter Chapter 3: Installing the Inverter Install the inverter either before or after the modules and power optimizers have been installed. NOTE l l Use only copper conductors rated for a minimum of 90°C/ 194°F. For the SE10KUS, SE20KUS, SE33.3KUS three phase inverters where opposite polarity DC conductors are routed in the same conduit, 1000V rated cables must be used.
Inverter Interfaces l ON/OFF/P Switch: Figure 10: ON/OFF/P switch o o o ON (1) - Turning this switch ON (after optimizer pairing) starts the operation of the power optimizers, enables power production and allows the inverter to begin exporting power to the utility grid. OFF (0) - Turning this switch OFF reduces the power optimizer voltage to a low safety voltage and inhibits exportation of power. When this switch is OFF, the control circuitry remains powered up.
Chapter 3: Installing the Inverter Figure 11: LEDs The following table describes system performance information by LED color and ON/OFF/P switch position. Indication ON/ OFF/ P switch position LED color Comment Red Green Blue S_OK: ON Power optimizers not paired OFF o S_OK: ON o No S_OK: OFF Blinking communication with the monitoring platform is established.
Inverter Interfaces Indication ON/ OFF/ P switch position LED color Comment Red Green Blue Percentage of AC Production: > 0 - 33 % OFF OFF OFF Percentage of AC Production: 0 - 33 % OFF ON OFF OFF OFF ON OFF ON ON Percentage of AC Production: 33 - 66 % Percentage of AC Production: 66 - 100 % l ON (1) This indicates power production as percentage of rated peak AC output power DC Safety Unit, including: o ON/OFF switch: connects and disconnects the DC power of the system o AC conduit en
Chapter 3: Installing the Inverter Opening Conduit Drill Guides This section describes how to open drill guides . CAUTION! SolarEdge does not permit opening or puncturing the Safety Switch in any location other than the predefined drill guide locations, or otherwise altering the construction of the enclosure, as this may compromise safety and will void the warranty. This includes, but is not limited to, the use of fasteners like rivets, screws, nails, inserts, or pins.
Mounting the Inverter Figure 14: Safety Switch drill guides NOTE Unused conduit openings and glands should be sealed with appropriate seals. Mounting the Inverter The inverter is typically mounted vertically, and the instructions in this section are applicable for vertical installation. Some three phase inverter models can be installed horizontally (above 10° tilt) as well as vertically, and at any tilt over 10° up to 90°. For information and instructions for horizontal mounting refer to http://www.
Chapter 3: Installing the Inverter 1. Determine the inverter mounting location, on a wall, stud framing or pole. It is recommended to mount the inverter in a location protected from direct sunlight. 2. To allow proper heat dissipation, maintain the following minimum clearance areas between the inverter and other objects: l l If installing a single inverter: o 8" (20 cm) from the top of the inverter.
Mounting the Inverter o o When installing inverters one above the other, leave at least 8" (20 cm) between the top of an inverter and the bottom of the Safety Switch.
Chapter 3: Installing the Inverter NOTE When mounting an inverter on an uneven surface, you may use spacers/ washers behind the top mounting hole of the bracket. Depending on the angle, use the appropriate size and number of spacers so that the bracket is perpendicular to the ground. Recommended: a stainless steel 3/4" long screw, with a 1/4" socket button head , two jam nuts and three washers. 5.
Mounting the Inverter l Verify that the bracket is firmly attached to the mounting surface. Figure 18: Safety Switch bracket 9. Insert the two supplied screws through the outer heat sink fin on both sides of the inverter and into the bracket (see Figure 17). Tighten the screws with a torque of 4.0 N*m / 2.9 lb.*ft. 32 -Three Phase System Installation Guide MAN-01-00527-1.
Chapter 4: Connecting the AC and the Strings to the Safety Switch Chapter 4: Connecting the AC and the Strings to the Safety Switch The Safety Switch disconnects all ungrounded DC conductors in compliance with the National Electric Code (NEC; Specifically NEC690.35, which addresses ungrounded PV arrays). The Safety Switch is rated to the maximum operating conditions of the inverter. Inverters of different models are equipped with different sizes/ types of terminal blocks.
Grid Connection Guidelines Grid Connection Guidelines l l l l l l Equipment grounding tightening torques: 4-6 AWG: 45 lb-in, 8 AWG: 40 lb-in, 10-14 AWG: 35 lb-in. The conduits, hubs and fittings must be suited for field wiring systems. The hubs and other fittings must comply with UL514B. Use only copper conductors rated for a minimum of 90°C. For the SE10KUS, SE20KUS, SE33.3KUS three phase inverters where opposite polarity DC conductors are routed in the same conduit, 1000V rated cables must be used.
Chapter 4: Connecting the AC and the Strings to the Safety Switch 2. Identify the fuse locations and the markings as described in Figure 21. Figure 21: Fuse locations and markings 3. Remove the dummy fuse from the 3-wire grid fuse holder and set it aside. 4. Move the fuse from the 4-wire grid fuse holder to the 3-wire grid fuse holder. 5. Place the dummy fuse in the 4-wire grid fuse holder. 6. During system setup, set the country to the appropriate 3-wire grid option.
Connecting the AC Grid to the Safety Switch To connect AC to ground: 1. Insert the grounding cable through the AC drill guide. 2. Connect the cable to the equipment grounding bus-bar. Tighten using a torque of 4.0 N*M / 35 lb-in. Figure 22: AC grounding in the Safety Switch NOTE The Safety Switches are equipped with different types of terminal blocks. The above figure is one example of the available Safety Switches. 36 -Three Phase System Installation Guide MAN-01-00527-1.
Chapter 4: Connecting the AC and the Strings to the Safety Switch To connect the AC grid to the Safety Switch – 14.4 & 33.3kW inverters: 1. Remove the spring-clamp terminal instructions from inside the switch. 2. Strip 1⅜'' (35mm) of the AC wire insulation. 3. Insert the AC conduit into the AC-side drill guide that was opened. NOTE Connect the equipment grounding before connecting the AC wires to the AC terminal block.
Connecting the AC Grid to the Safety Switch To connect the AC grid to the Safety Switch – 9kW, 10kW, 20kW: 1. Strip 05⁄16'' (8mm) of the AC wire insulation. 2. Insert the AC conduit into the AC-side drill guide that was opened. NOTE Connect the equipment grounding before connecting the AC wires to the AC. Veillez à relier le conducteur de PE (la terre) avant de connecter les fils CA au bornier CA. 3. Connect the wires as follows: a.
Chapter 4: Connecting the AC and the Strings to the Safety Switch Connecting the Strings to the Safety Switch You can connect systems with multiple DC strings in parallel to the DC input terminals of the switch. Inverters have one, two or three pairs of DC input terminals, depending on the inverter power rating. If more strings are required, they can be connected in parallel using an external combiner box before connecting to the switch.
Connecting the Strings to the Safety Switch Figure 25: DC Spring-clamp terminal example - 9kW, 10kW and 20kW inverters l For three phase inverters 14.4kW and 33.3kW – Connect the DC wires from the PV installation to the DC+ and DC- terminal blocks : a. Insert the screwdriver into the front opening and rotate it counterclockwise to activate the clamp mechanism. The side latch holds the clamp in the open position. b. Insert the wire into the side opening as deep as possible. c.
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter SetApp If applicable, you can connect communication options at this stage, as described in Setting Up Communication on page 51. Once all connections are made, the system should be activated and commissioned using the Inverter SetApp mobile application.
Step 2: Commissioning and Configuring the Installation Step 2: Commissioning and Configuring the Installation This section describes how to use the SetApp menus for commissioning and configuring the inverter settings. Menus may vary in your application depending on your system type. To access the Commissioning screen: Do one of the following: l During first time installation: Upon Activation completion, in the SetApp, tap Start Commissioning. The main Commissioning menu screen is displayed.
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter 3. When Pairing Complete is displayed, the system startup process begins: Since the inverter is ON, the power optimizers start producing power and the inverter starts converting AC. WARNING! When you turn ON the inverter ON/OFF/P switch, the DC cables carry a high voltage and the power optimizers no longer output a safe 1V output.
Device Manager For P(Q) diagram refer to https://www.solaredge.com/sites/default/files/application_ note_p_q_diagram_of_se_inverters_en_and_na.pdf. NOTE SolarEdge inverters with “Grid Support” functionality (as marked on the inverter certification label), are compliant with UL 1741 Supplement A. The functionality is built into the inverter and no additional external device is required.
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter NOTE Please have these numbers ready when you contact SolarEdge Support.
Main Inverter Status Main Inverter Status Status Inverter SN 07318000C Power Voltage Frequency 50 kW 230Vac 50 Hz P_OK: 15 of 20 Server Comm. Optimizers Connected S_OK (LAN) Status Switch Production OFF CosPhi Limit Country 1.00 No Limit USA2 Voltage Temp Fan 350 Vdc 156 F N/A Switch Off.
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter Site Status The Site status screen shows the accumulated status of all inverters connected to a master inverter in a chain (bus) and the master inverter status. Status Site Production Limit Inverters 90 kW 1.00 MW 10/10 Inverter SN 07318000C Power Voltage 100 kW 277 Vac Frequency 60.9 Hz P_OK: 31 0f 31 S_OK Optimizers Connected Server Connected Status Switch Production OFF CosPhi Limit Country 1.
Inverter Energy Status l l l l l l NC: Not Connected. Refer to Troubleshooting Communication on page 62 S_OK: The connection to the monitoring platform is successful (should appear only if the inverter is connected to the server) N/A : Not Applicable x of y: Number of devices connected out of all devices Temporarily displayed (with a clock sign): o Initializing communication o Connecting to a network o Connecting to SolarEdge servers Error message (with the sign).
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter l Energy: The total energy read by the meter. The value displayed in this line depends on the meter type connected to the inverter and its location: o If a bidirectional meter is connected at the consumption point, this value is the consumed energy. o If the meter is installed at the production connection point, this value is the energy produced by the site.
Designer Designer Designer recommends inverter and power optimizer selection per site size and enables report generation.You can create a project in Designer and export the site design with the string layout to the monitoring platform. For more information, refer to https://www.solaredge.com/products/installertools/designer#/.
Chapter 6: Setting Up Communication Chapter 6: Setting Up Communication The inverter sends the following information to the monitoring platform: l Power optimizer information received via the DC power lines (the PV output circuit) l Inverter information l Information of any other connected devices This chapter describes setting up communication between: l the inverter and the monitoring platform through the Internet (wired/ wireless), or through a cellular connection l multiple inverters for a master/slave
Cellular (GSM, CDMA) Cellular (GSM, CDMA) This wireless communication option (purchased separately) enables using a cellular connection to connect one or several devices (depending on the data plan used) to the monitoring platform. The GSM/CDMA Plug-in is provided with a user manual, which should be reviewed prior to connection. Refer to https://www.solaredge.com/sites/default/files/cellular_gsm_ installation_guide_for_inverters_with_setapp.pdf and https://www.solaredge.
Chapter 6: Setting Up Communication Communication Connectors Two communication glands are used for connection of the various communication options. Each gland has three openings. The table below describes the functionality of each opening. Unused openings should remain sealed. Gland# Opening Functionality Cable Size (diameter) One small External antenna cable 2-4 mm Two large Ethernet connection (CAT5/6) or Cellular 4.5-7 mm All three RS485 2.5-5 mm 1 (PG16) 2 (PG13.
Removing the Inverter Cover Removing the Inverter Cover If the inverter cover is not already removed, use the following procedure for cover removal. To remove the inverter cover 1. Turn the inverter ON/OFF/P switch to OFF. Wait 5 minutes for the capacitors to discharge. 2. Turn the Safety Switch to OFF. 3. Disconnect the AC to the inverter by turning OFF the circuit breakers on the distribution panel. 4.
Chapter 6: Setting Up Communication To connect the Ethernet cable: 1. Remove the inverter cover as described in Removing the Inverter Cover on page 54. 2. Open the communication gland #1. CAUTION! The gland includes a rubber waterproof fitting, which should be used to ensure proper sealing. ATTENTION! Le cote interne du gland contient une rondelle qui doit être utilisée pour une bonne étancheïté. 3. Remove the plastic seal from one of the large opening . 4.
Creating an Ethernet (LAN) Connection 6. Use a pre-crimped cable to connect via gland #1 to the RJ45 plug on the inverter's communication board or, if using a spool of cable, connect as follows: a. Insert the cable through gland #1. b. Remove the cable’s external insulation using a crimping tool or cable cutter and expose eight wires. c. Insert the eight wires into an RJ45 connector, as described in Figure 31. d. Use a crimping tool to crimp the connector. e.
Chapter 6: Setting Up Communication Creating an RS485 Bus Connection The RS485 option enables creating a bus of connected inverters, consisting of up to 31 slave inverters and 1 master inverter. Using this option, inverters are connected to each other in a bus (chain), via their RS485 connectors. The first and last inverters in the chain must be terminated as described on page 59. RS485 wiring specifications: l Cable type: Min.
Creating an RS485 Bus Connection 4. Loosen the screws of pins A(+), B(-), and G on the left of the RS485 terminal block (RS485-1 or RS485-2). Figure 34: RS485 terminal block 5. Insert the wire ends into the G, A and B pins shown above. Use Four- or six-wire twisted pair cable for this connection.
Chapter 6: Setting Up Communication 10. Terminate the first and last SolarEdge device in the chain by switching a termination DIP-switch inside the inverter to ON (move the left switch up). The switch is located on the communication board and is marked SW7SW1. Figure 36: RS485 termination switch NOTE Only the first and last SolarEdge devices in the chain should be terminated. The other inverters in the chain should have the termination switch OFF (down position). 11.
Verifying the Connection 1. Access the Status screen: a. If not already ON - turn ON AC to the inverter by turning ON the circuit breaker on the main distribution panel. b. Open SetApp and follow the instructions on the screen (scan the inverter bar-code; move the ON/OFF/P switch to P position (for less than 5 sec) and release). The mobile device creates a Wi-Fi connection with the inverter and displays the main Commissioning screen. 2.
Appendix A: Errors and Troubleshooting Appendix A: Errors and Troubleshooting This appendix describes general system problems, and how to troubleshoot them. For further assistance, contact SolarEdge Support. Identifying Errors Errors may be indicated in various system interfaces: On the inverter bottom panel, a red LED indicates an error. In the monitoring platform and the SetApp, errors are displayed with codes.
Troubleshooting Communication 2. Right-click the inverter and select Info from the menu (Figure 37). The inverter details window is displayed (Figure 38). Figure 37: Inverter menu 3. Click the Errors tab. The list is displayed. Figure 38: Inverter details - Error list Troubleshooting Communication Troubleshooting Ethernet (LAN) Communication The possible errors and their troubleshooting are detailed in the following table: 62 -Three Phase System Installation Guide MAN-01-00527-1.
Appendix A: Errors and Troubleshooting Error Message LAN cable disconnected No DHCP Configure Static IP or set to DHCP Cause and Troubleshooting Physical connection fault. Check the cable pin-out assignment and cable connection. IP settings issue. Check the router and inverter configuration. Consult your network IT. Gateway not responding Ping to router failed. Check the physical connection to the switch/ router. Check that the link LED at the router /switch is lit (indicating phy-link).
Power Optimizer Troubleshooting Power Optimizer Troubleshooting Possible cause and troubleshooting Problem Power optimizers are shaded. If you connected the inverter to the monitoring platform, retry pairing remotely (during sunlight). Make sure to leave the inverter ON/OFF switch ON and that S_OK appears in the status screen. Pairing failed Power optimizer (s) output is disconnected. String voltage is 0V Connect all power optimizer outputs. Power optimizer(s) not connected in the string.
Appendix B: Mechanical Specifications Appendix B: Mechanical Specifications Figure 39: Three phase inverter with bracket - front, side and rear views Figure 40: Inverter mounting bracket -Three Phase System Installation Guide MAN-01-00527-1.
Appendix C: External Fan Maintenance and Replacement Appendix C: External Fan Maintenance and Replacement The inverter has two fans: one is internal and the other is accessible from the outside of the inverter. A fan replacement kit is available from SolarEdge. Figure 41: Inverter external fan Fan Maintenance At least once a year, open the fan screen and clean the accumulated dust using a brush.
Appendix C: External Fan Maintenance and Replacement 8. After powering up the inverter, check the fan status on SetApp: Select Commissioning è Status. ð -Three Phase System Installation Guide MAN-01-00527-1.
Appendix D: Replacing and Adding System Components Appendix D: Replacing and Adding System Components This appendix includes replacement procedures for the SolarEdge system components. For inverter or Safety Switch replacement, typically only the part to be replaced is supplied (not both inverter and Safety Switch). In this case, the Safety Switch should be disconnected from the inverter as described herein.
Appendix D: Replacing and Adding System Components 8. Place the new inverter on the mounting bracket; insert the screws securing the inverter to the mounting bracket. 9. Screw the two conduit nuts in the inverter securing the Safety Switch to the inverter. 10. Connect the DC and AC wires to the inverter. 11. If ferrite beads were removed from the DC and AC wires, place them on the wires and close them.
Connecting the Safety Switch to the Inverter 3. Attach the Safety Switch with its bracket to the wall and slightly close the screws. Do not over tighten. 4. Securely screw the two conduit nuts onto the conduit ends in the inverter. Verify proper conduit sealing. Connecting the Safety Switch to the Inverter 1. If ferrite beads were removed from the DC and AC wires, place them on the wires and close them.
Appendix D: Replacing and Adding System Components 7. Ensure proper conduit sealing; inspect the entire conduit run and use standard conduit sealants to avoid water penetration. Adding, Removing, or Replacing Power Optimizers 1. Turn OFF the inverter ON/OFF/P switch, and wait until the green LED is blinking , indicating that the DC voltage is safe (<50V), or wait five minutes before continuing to the next step. 2.
Technical Specifications - Three Phase Inverters (North America) Technical Specifications - Three Phase Inverters (North America) SE9KUS SE10KUS SE14.4KUS 120 / 208 277 / 480 120 / 208 Rated AC power output 9000 10000 14400 20000 Maximum AC power output 9000 10000 14400 20000 Supported grid SE20KUS SE30KUS SE33.
Technical Specifications - Three Phase Inverters (North America) SE9KUS SE10KUS SE14.4KUS SE20KUS SE30KUS SE33.3KUS Units STANDARD COMPLIANCE Safety UL1741, UL1741 SA, UL1699B, CSA 22.2, Canadian AFCI according to T.I.L.
Technical Specifications - Three Phase Inverters (North America) Default Trip Limits and Times According to IEEE1547 NOTE The inverters are equipped with adjustable utility protective function set-points, and can be aggregated above 30kW on a single Point of Common Connection. The default settings are in compliance with IEEE1547. Utility authorization is required to change these set-points. Voltage Range (% of Base Voltage) Max. Clearing Time (Sec) V < 50% 0.16 50 % < V < 88% 2.00 110% < V < 120% 1.