StorEdge Wiring Quick Guide and On Site Checklist for RESU10H Battery

1
StorEdge™ Wiring Guide & On Site Checklist for North America
This document is a battery wiring guide and contains an on-site checklist with steps for post-installation verification of a StorEdge system, for the following batteries:
LG Chem RESU10H
For more details, please refer to the StorEdge Installation Guide supplied with the StorEdge Inverter. For additional assistance contact SolarEdge Support (refer to
Support and Contact Information on page 9).
Wiring Guide
WARNING!
For LG Chem RESU10H batteries:
Before wiring the system, make sure that the battery is powered off, using both of the following switches:
* Auxiliary power supply switch
* Circuit breaker switch
Figure 1: LG Chem Auxiliary Power Switch and Circuit Breaker Switches