l Frame-mountedpoweroptimizersaremounteddirectlyonthemoduleframe,
regardlessofrackingsystem(rail-lessorwithrails).Forinstallationofframe-mounted
poweroptimizers,refertohttp://www.solaredge.com/sites/default/files/installing_
frame_mounted_power_optimizers.pdf.
l Thestepsinthischapterrefertomoduleadd-onpoweroptimizers.Forsmart
modules,startfromStep3:ConnectingPowerOptimizersinStringsonpage19.Also
refertothedocumentationsuppliedwiththesmartmodules.
l Thepoweroptimizercanbeplacedinanyorientation.
l Ifconnectingmoremodulesthanoptimizerinputsinparallel,useabranchcable.Somecommercial
poweroptimizermodelshaveadualinput.
l Positionthepoweroptimizercloseenoughtoitsmodulesothattheircablescanbeconnected.
l Makesuretousepoweroptimizersthathavetherequiredoutputconductorlength:
o
Donotuseextensioncablesbetweenamoduleandapoweroptimizer,betweentwomodules
connectedtothesameoptimizer,orbetweentwooptimizersotherthaninthecasesspecified
below.
o
Youcanuseextensioncablesbetweenpoweroptimizersonlyfromrowtorow,aroundobstacles
withinarow,andfromtheendofthestringtotheinverter,aslongasthemaximumdistanceis
notexceeded.
NOTE
l Use at least 11 AWG/ 4 mm² DC cables.
l The total cable length of the string (excluding power optimizers’ cables) should not exceed
1000ft./300 m from DC+ to DC- of the inverter.
l Theminimumandmaximumstringlengthguidelinesarestatedinthepoweroptimizerdatasheets.
RefertotheDesignerforstringlengthverification.TheDesignerisavailableontheSolarEdgewebsite
athttps://www.solaredge.com/us/products/installer-tools/designer#/.
l Completelyshadedmodulesmaycausetheirpoweroptimizerstotemporarilyshutdown.Thiswill
notaffecttheperformanceoftheotherpoweroptimizersinthestring,aslongastheminimum
numberofunshadedpoweroptimizersconnectedinastringofmodulesismet.Ifundertypical
conditionsfewerthantheminimumoptimizersareconnectedtounshadedmodules,addmore
optimizerstothestring.
l Equipmentgroundingtighteningtorques:4-6AWG:45lb-in,8AWG:40lb-in,10-14AWG:35lb-in.
l Toallowforheatdissipation,maintaina2.5cm/1"clearancedistancebetweenthepoweroptimizer
andothersurfaces,onallsidesexceptthemountingbracketside.
Figure 4: Power optimizer clearance