Install Manual
Table Of Contents
- Disclaimers
- Revision History
- Support and Contact Information
- Contents
- HANDLING AND SAFETY INSTRUCTIONS
- IMPORTANT SAFETY INSTRUCTIONS
- Chapter 1: Introducing the SolarEdge Power Harvesting System
- Chapter 2: Installing the Power Optimisers
- Chapter 3: Installing the Inverter
- Chapter 4: Connecting the AC and the Strings to the Safety Switch
- Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter SetApp
- Chapter 6: Setting Up Communication
- Appendix A: Errors and Troubleshooting
- Appendix B: Mechanical Specifications
- Appendix C: Replacing and Adding System Components
- Technical Specifications - Single Phase Inverters with HD-Wave Technology (No...
l Hardware IDs:DisplaysthefollowingHWserialnumbers(ifexist,andconnectedtotheinverter):
o
This inverter:theinverter'sID
o
Meter #:EnergymeterID(upto3meterscanbeconnected)
o
ZB:ZigBeePlug-inMACaddress
o
Cell:MEID(CDMA)orIMEI(GSM)
l Error Log:Displaysthelastfiveerrors,andenablesresetting(clearing)thelog.
l Warning Log:Displaysthelastfivewarnings,andenablesresetting(clearing)thelog.
Step 3: Verifying Proper Activation and
Commissioning
1. SelectInformationandverifythatthecorrectfirmwareversionsareinstalledoneachinverter.
2. SelectStatusandverifythatinverterisoperatingandproducingpower(seealsoViewingSystem
Statusonpage38).
3. VerifythatadditionalconfigurationswereproperlysetbyviewingtherelevantStatusscreens.
4. VerifythatthegreeninverterLEDissteadilylit.
YourSolarEdgepowerharvestingsystemisnowoperational.
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter
-Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.0