Three Phase Inverter with Synergy Technology Quick Installation Guide PN: SExxK-xxxxIxxxx Scan for full installation guide For North America Version 1.
Legend NOTE ON CAUTION! ON This symbol denotes information intended to assist the user in making optimum use of the product. Denotes a hazard. It calls attention to a procedure that, if not correctly performed or adhered to, could result in damage or destruction of the product. Do not proceed beyond a caution sign until the indicated conditions are fully understood and met. ! WARNING! Denotes a hazard.
Installing the Power Optimizers 1 2 3 4 5 6 1 2 Use SolarEdge Designer to design SE system https://designer.solaredge.com Download SolarEdge Mapper to map string Power Optimizers 1 Download MAN-01-00786-1.
1 Installing the Power Optimizers 1 2 3 4 5 6 3 4 Scan QR code using Mapper Install Power Optimizer 10 mm / 0.4" 25 mm / 1" (P860, P960) M6 (1/4’’) or M8 (5/16”) stainless steel 9.5 N*m / 7 lb*ft 12.7 mm / 0.5” 10 mm / 0.4" 25 mm / 1" (P860, P960) Complete site registration and physical layout in the Monitoring platform 2 MAN-01-00786-1.3 10 mm / 0.4" 25 mm / 1" (P860, P960) 10 mm / 0.
Installing the Power Optimizers 1 2 3 4 5 6 1 5 Connect input from Module 6 Connect output to String 2:1 series connection Use a dual input optimizer (P800p) for parallel connection of two PVs or use a branch cable to connect two PVs to a single input optimizer. MAN-01-00786-1.
2 Connecting the PV Array Check array polarity. Verify 1±0.1V per optimizer Example: 8 optimizers = ~8V 8V + 4 MAN-01-00786-1.
Maintaining Clearance 10 cm / 4” 40 cm / 16” 15 cm / 6” 5 cm / 2” Indoor Clearance 20 cm / 8” where annual average high temperature equals or above 25˚C / 77˚F Outdoor Clearance ! 40 cm / 16” Horizontal Installation WARNING! Area in front of the inverter must be kept clear for at least one meter CAUTION! Do not block Airflow 100.8 cm / 39.68” 3 On mesh fence Keep more than 10° On metal back sheet Back to back 30 cm / 11.8” 20 cm / 8” 114.5 cm / 45” 40 cm / 16” MAN-01-00786-1.
4 Marking & Drilling Holes Drill holes 5 1 6.1” / 15.5 cm Level provided template horizontally 6.1” / 15.5 cm 3.3” / 9.3 cm 3.3” / 9.3 cm 2 Optional Optional Mark holes Ø 9mm / 0.35” Avoid wobbly installation by adding back support 3 Position provided template vertically Optional unit - model dependent 7.36” / 18.7 cm Mark holes 4 CAUTION! Do not block airflow 6.53” / 16.6 cm 6 MAN-01-00786-1.
Mounting the Units 1 2 1 3 5 2 2.9 lb.*ft. For left or right units, use only the outer screw 4 4 2.9 lb.*ft. 3 2.9 lb.*ft. 2.9 lb.*ft. 18KG 32KG MAN-01-00786-1.
6 Connecting Cables 1 2 Align pin grooves in connector with pin guides in socket Connect cables according to labels CAUTION! Do not block Airflow Boundary for single conduit entry. Max conduit size 3” Max conduit size 2” 8 MAN-01-00786-1.3 Max conduit CAUTION! Remove plates from unit before drilling holes size 2.5” 1.
Removing Covers 1 7 ! WARNING OFF OFF 2 DISCONNECT POWER BEFORE BEGINNING INSTALLATION 4 3 MAN-01-00786-1.
8 Connecting PV Strings (Option 1) 1 When using a stranded wire, use of ferrule is at the installer discretion 6 - 12 AWG 0.7” 18 mm + Ground conduit nut if required by regulation Up to 12 Strings 10 MAN-01-00786-1.
Connecting PV Strings (Option 2) 8 Synergy Units Left Center Right Left Center Right DC+ 4 AWG: 3.7 lb.*ft 3 – 2 AWG: 5.9 lb.*ft 2.2 lb.*ft. DC- 4-14 AWG Ground conduit nut if required by regulation - + Important: When installing a system with more than 3 strings per a single Synergy Unit (whether connected directly or via a combiner box), fuses are required. In SolarEdge system, Ferrule 25A fuses shall be used Max 2 AWG Fine stranded Combiner Box MAN-01-00786-1.
9 Connecting AC and Protective Earth The inverter can either support 4 wire + PE or 3 wire + PE connection Overcurrent protection for the AC output must be provided by others, see manual for guidance Max 1.39” / 33 mm 5 6 Connect PE wire first 1 4 3 Ø 0.5” / 10 mm 2 Max thickness 0.27” / 7mm 15.4 lb.*ft. One-hole, standard barrel, compression lugs only, 600V • For aluminum wires, USE ONLY aluminum lugs • For copper wires, USE ONLY copper tin-plated lugs PE Wire 10 – 4 AWG: 3.7 lb.
LAN Communication 10 2 1 COMM 1 4 lb*ft Ethernet 3 MAN-01-00786-1.
11 RS485 Connection of Multiple Inverters A Move SW1 switch to ON (up) to terminate first and last inverters on RS485 bus COMM 2 SW1 6 1 2 3 lb*ft 7 SW1 3 SW1 SW1 G A+ BG A+ B- G A+ B- G A+ B- CAT6, 3-wire, shielded, twisted pair (0.2- 1 mm²) max 1km / 3300 ft. 14 MAN-01-00786-1.
Connecting Wi-Fi Communication (Optional) 12 1 4 5 2 4 lb*ft 3 MAN-01-00786-1.
13 Connecting Cellular Communication (Optional) 1 4 5 2 3 16 MAN-01-00786-1.
Installing Covers 14 2 3 2.6 lb*ft 3 1 5 11 6 2 4 MAN-01-00786-1.
15 Pre-commissioning when AC Power is Not Connected (Option 1) 1 Download SolarEdge SetApp 2 Turn switch to ON 3 Connect power bank A 4 Start and follow SetApp ON Start Download Power bank: 60W output port , USB-C Power Delivery (PD): 20V 3A (not provided) Cover connector when not used 3.3 ft / 1 meter, USB-C / USB-C (not provided) 5 Disconnect and remove power bank 6 Turn switches to OFF 7 Wait until inverter turns-off (all LEDs turn-off) 18 MAN-01-00786-1.
Commissioning with DC and AC Power (Option 2) 1 2 3 Download SolarEdge SetApp Turn switches to ON Start & follow SetApp 16 ON Start Download ON MAN-01-00786-1.
17 Commissioning the Leader Inverter A Commissioning 1 Country & Language 2 Pairing 3 Site Communication RS485-1 Protocol SolarEdge Solaredge Leader RS485-1 Follower Detect Inverter Units 4 20 MAN-01-00786-1.
LED Indications 18 A POWER Green COMM Blue FAULT Red System is producing Power AC is connected but the system is not producing power Inverter is communicating with the monitoring platform System error MAN-01-00786-1.
Support Contact Information If you have technical problems concerning SolarEdge products, please contact us: https://www.solaredge.com/service/support Subject to change without notice. Copyright © SolarEdge Inc. All rights reserved. July 2021.