Install Manual

Table Of Contents
3.
Insert the conduit with the AC line and PE wires through ACopening at the bottom
of the Synergy Manager.
CAUTION!
Ground the conduit nut if required by regulation.
NOTE
Connect the equipment grounding before connecting the AC wires to the
AC terminal block.
Veillez à relier le conducteur de PE (la terre) avant de connecter les fils CA
au bornier CA.
4. Expose 10 - 11 mm 0.4 - 0.43" of the PE wire insulation
5.
Connect the PE wire to the PE terminal and fasten the Allen screw with a torque of
11 lb.*ft.
NOTE
When using a stranded wire, use of ferrule is at the installer discretion.
Figure 23: Connecting of PE (grounding) wire
To connect AC:
1.
Verify that the main AC circuit breaker in OFF position at the circuit breakers panel.
2.
Remove the AC terminal block cover.
Chapter 4: Connecting AC and PV Strings to the Synergy Manager 49
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx