Installation Guide

o
Wheninstallinginverterssidebyside,followtheseclearance
specifications:
Single Phase
Inverters
Three Phase
Inverters
Locations where the yearly average
high temperature is below 25˚C/7 F
20 cm / 8"
between inverters
20 cm / 8"
between inverters
Locations where the yearly average
high temperature is above 25˚C/77˚ F
40 cm / 16"
between inverters
l Positionthemountingbracketagainstthewall/poleandmarkthedrillinghole
locations(refertoMechanical Specificationsonpage109forinverterand
mountingbracketdimensions):
o
ForType1-EnsurethattheU-shapedindentationsarefacingupandthe
“UP”markingiscorrectlyoriented,asshownbelow:
Figure 15: Bracket with U-shaped indentations facing up
o
ForType2–Ensurethattheflatsideofthebracketisatthebottom,asin
Figure 14.
o
Useatleasttwobracketholes.Additionalholescanbeusedtofixthe
bracket.Determinewhichandhowmanyholestouseaccordingto
mountingsurfacetypeandmaterial.
2. Drilltheholesandmountthebracket.Verifythatthebracketisfirmlyattachedtothe
mountingsurface.
Chapter 3: Installing the Inverter
SolarEdge-Installation Guide MAN-01-00002-4.0
29