Installation Guide

To connect the AC grid to the Safety Switch – single phase
10-11.4kW inverters:
1. Removethespring-clampterminalinstructionsfrominsidetheswitch.
2. Strip1⅜''(35mm)oftheACwireinsulation.
3. InserttheACconduitintotheAC-sideknockoutthatwasopened.
NOTE
Connect the equipment grounding before connecting the AC wires to the AC terminal
block.
Veillez à relier le conducteur de PE (la terre) avant de connecter les fils CA au bornier CA.
4. Connectthewirestotheappropriateterminalblocksaccordingtothelabelsonthe
terminalblocks(N,Gnd,L1andL2).
5. Usea13/64"(5mm)straightflat-bladescrewdrivertoconnectthewirestotheterminals:
l Insertthescrewdriverintothetopopeningandrotateitcounterclockwisetoactivate
theclampmechanism.Thesidelatchholdstheclampintheopenposition.
l Insertthewireintothesideopeningasdeepaspossible.
l Slightlyrotatethescrewdrivercounter-clockwisetoreleasethelatch.
l Removethescrewdriver–thewireissafelyclamped.

Figure 27: AC Spring-clamp terminal examples - single phase 7.6-11.4kW inverters
6. Verifythattherearenounconnectedwires.
Chapter 4: Connecting the AC and the Strings to the Safety Switch
SolarEdge-Installation Guide MAN-01-00002-4.0
39