Installation Guide

Chapter 5: Commissioning the Installation
Thischapterdescribeshowtoactivatethesystem,pairthepoweroptimizerstotheinverter
andverifytheproperfunctioningofthesystem.
Step 1: Activating the System
1. VerifythattheON/OFFswitchisOFF.
2. TurnONtheACbreaker.
3. MovetheSafetySwitchtotheONposition.
4. Ifnotalreadyremoved,removetheinvertercover:Opentheinvertercover’ssixAllen
screwsandcarefullypullthecoverhorizontallybeforeloweringit.
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when the inverter
cover is removed.
RISQUE DÉLECTROCUTION, ne touchez pas les fils non isolés lorsque le couvercle
de l'onduleur est retiré.
5. Activatetheinverteraccordingtotheactivationinstructionssuppliedintheinverter
package:
a. VerifycardS/NmatchesinverterS/N.
b. Insertthecardintoslotmarked"CARD"onthecommunicationboard.
c. TurnACON.
d. LCDshows:RunningScript...èDone!
e. IfLCDshows:Scripterror,contactSolarEdgeSupport.
6. Verifythattheinverterisconfiguredtothepropercountry:PresstheLCDlightbutton
untilreachingtheIDstatusscreen:
I D : # # # # # # # # # #
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
C P U : 0 0 0 3 . 1 4 x x
C o u n t r y : U S A 1
7. Ifrequired,performthefollowingadditionalsteps:
l CountrysettingsorinverterconfigurationusingtheinternalLCDuserbuttons–referto
Country and Gridonpage57.
l Communicationoptionsconnection–refertoSetting Up Communicationonpage71.
Chapter 5: Commissioning the Installation
SolarEdge-Installation Guide MAN-01-00002-4.0
43