Installation Guide

3. Waitforthecompletionofthepairing(remainingsecondsis0).Ifpairingfails,anerroris
displayed.Inthiscase,repeatthepairingsteps,andrefertoPower Optimizer
Troubleshooting onpage94.Iftheproblempersists,contactSolarEdgeSupport.When
pairingsucceeds,thefollowingmessageisdisplayed:
P a i r i n g
P a i r i n g C o m p l e t e d
4. Thesystemstartupprocessbegins:
5. SincetheinverterisON,thepoweroptimizersstartproducingpowerandtheinverter
startsconvertingAC.
NOTE
When you turn ON the inverter ON/OFF switch, the DC cables carry a high voltage and
the power optimizers no longer output a safe 1V output.
Après avoir mis l'interrupteur ON/OFF de l'onduleur monophasé sur ON, les câbles DC
portent une haute tension et les optimiseurs de puissance ne génèrent plus la tension de
sécurité de 1V.
6. WhentheinverterstartsconvertingpoweraftertheinitialconnectiontotheAC,the
inverterentersStandbymodeuntilitsworkingvoltageisreached.Thismodeisindicated
bytheflickeringgreeninverterLED.
7. WhiletheinverterisinStandbymode,itmonitorsthegridandverifiescorrectgrid
voltageandfrequency.Thefollowingmessageisdisplayed:
W a k i n g U p . . .
R e m a i n i n g : 0 5 1 S e c
ThecountdownindicatesthesecondsremaininguntilenteringtheProduction
mode.Thistimeisinaccordancewithlocalregulationsandistypicallybetween
threetofiveminutes.
Whencountdowniscomplete,theinverterentersProductionmodeandproducespower.
ThesteadilylitgreeninverterLEDindicatesthismode.
8. Forsingle phase inverters only-scrolltotheMaintenancemenuandselectOptimizer
Conf.èSet Rapid ShutdownèEnable.
S e t R a p i d S h u t d o w n
E x i t
SolarEdge-Installation Guide MAN-01-00002-4.0
46
Step 2: Pairing Power Optimizers to the Inverter