Installation Guide
SOUTHWEST WINDPOWER DOCUMENT 0228 REV A
14
10) Run the turbine wires through the tower base and slide in the tower pipe. Tighten the set
screw in the tower base to 8-10 ft.*lb. of torque.
Step 7: Attaching Guy Wires to Anchors
With the assembled tower laying on the ground the guy wires at the sides and rear of the tower
should be attached now. Make sure that the bottom of the tower is positioned at the tower base so
that the distances from the anchors to the guy wire attachment points on the tower will be the
same as when the tower is vertical. Leave about 6 inches of slack in the wires to allow for any
misalignment or unnoted elevation differences (the wires will be adjusted more precisely later).
The side wires can be pulled to their anchors and attached using the wire rope thimbles provided
with your tower kit.
Note: The thimbles may need to be spread open to install them on your anchors. This can be done
with a pair of pliers. Be sure to press the open end of the thimbles back together (with pliers)
before attaching the guy wires.
The rear wire length can be estimated by pulling it to a side anchor and placing a piece of tape on
the wire at the distance of the side anchor. The rear wire will then be attached to its respective
anchor at the point marked by the tape. This should make its length approximately correct when
the tower is up (again, it will be readjusted, so don’t worry about a few inches one way or the
other). Make sure that none of the guy wires are crossed and that the side wires are straight
without the rear wire crossed on top of them! Run the tail of the guy wire through the second
clamp twice, forming a safety loop (as shown on page 15). Attach the side and rear wires
securely as shown in the drawing with two clamps on each wire. Use 6-8 ft.-lb. of torque on each
nut. It is important (for good strength) that the saddle part of each clamp is on the loaded (tower)
side of the guy wire.