Instructions / Assembly

1
40269-469-02
03/2006
Lexington, KY, USA
Replaces 40269-469-01 03/1983
Instruction Bulletin
QO
®
Circuit Breaker Load Centers
Retain for future use.
INSTALLATION
Remove Knockouts
1. Turn off all power supplying this equipment before working on or inside
equipment.
2. Drive center knockout inward and alternately pry up or drive in outer rings,
one at a time.
Mount Box
Position box so marking is up for top feed and down for bottom feed.
Pull Conductors Into Box
NOTE: Conductors must enter the box through approved wire clamps, conduit
bushing or by other methods approved for the purpose, to prevent damage to
conductor insulation.
Figure 1: Wire Mains and Neutral
DANGER
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
Apply appropriate personal protective equipment (PPE) and follow safe electrical work
practices. See NFPA 70E.
This equipment must only be installed and serviced by qualified electrical personnel.
Turn off all power supplying this equipment before working on or inside equipment.
Always use a properly rated voltage sensing device to confirm power is off.
Replace all devices, doors and covers before turning on power to this equipment.
Failure to follow these instructions will result in death or serious injury.
Line
Line
Main Lugs (125 A Max.) Main Circuit Breaker (125 A Max.)
Main Lugs (225 A Max.)
Main Circuit Breaker (225 A Max.)
40269-469-02.fm Page 1 Thursday, April 20, 2006 9:23 AM

Summary of content (4 pages)