Installing the ½” copper to and from the collector using 
the compression fittings.
1.  Push the union nut   and 
the cutting ring   onto the 
copper pipe  . The pipe 
must  protrude  at  least  3/8”  
(3 mm) from the cutting ring 
in order to ensure the force 
transmission and the sealing. 
2.  Insert the support sleeve  into 
the copper pipe. 
3.  Insert the copper pipe with the 
plugged-on individual parts (, 
 and ) all the way into the 
housing of the compression 
fitting .
4.  First screw the union nut  
manually. 
5.  Tighten the union nut   by 
rotating one full turn. Hold the 
housing of the compression 
fitting  to avoid rotation in order 
to avoid damaging the sealing 
ring.
Figure 24.
PLUMBING CONFIGURATION 
1 2
3 4
1.  ½” copper tube -  from 
the collector outlet 
(top) to the collector 
return compression 
fitting.
2.  ½”  copper  tube  – 
from the collector 
inlet (bottom) to 
the collector supply 
compression fitting.
3.  ¾”  copper  tube  – 
from the upper tank 
inlet  marked  “from 
collector”  to  the  tank 
supply threaded fitting.
4.  ¾” copper tube – from 
the lower tank outlet 
marked “to pump”  
to the tank return 
threaded fitting.
Figure 25.
FUNCTION 
Check valves
The solar station is equipped with check valves in the supply 
and the return ball valve (J, Q). 
For filling, venting and flushing of the installation the check 
valves must be turned to the correct position. To set the 
proper position for the check valves take off the temperature 
gauges (C, E), remove the top cover (D) and turn the ball 
valves into the proper position using a wrench. See Figure 
26. In the 45° position the balls in the ball valves push the 
check valves open.
During operation the ball valves must be in 0° position.
0° 45° 90°
Check valve is 
operating, flow 
only in flow 
direction
Check valve is not 
operating, flow in 
both directions.
Ball valve 
closed, 
no flow.
Figure 26.
FLOWMETER 
The flowmeter serves to measure and display flow volume 
of the system in a range of 0.5-5.0 US gpm.
In order to guarantee the flawless function of the measuring 
device the installation must be flushed and free from foreign 
substances.
The flowmeter must be mounted vertically.
LEFT SCALE:
0.5 - 3.5 GAL/MIN
READING EDGE =
TOP EDGE OF THE
TURBINE
EXAMPLE:
ABOUT 2 GAL/MIN
RIGHT SCALE:
4 - 5 GAL/MIN
READING EDGE =
BOTTOM EDGE OF
THE TURBINE
Figure 27.