INSTALLATION
Commissioning
11. Commissioning
WARNING Electrocution
Commissioning may only be carried out by a qualified
contractor in accordance with safety regulations.
11.1 Initial start-up
30
60
45
35
40
50
55
°C
el ectronic
30
60
45
35
40
50
55
°C
el ectronic
..
2..
26�02�02�1183
Open and close all connected draw-off valves several times,
until all air has been vented from the pipework and the
appliance.
Check for leaks in the appliance screw joints.
Activate the safety pressure limiter for flow pressure by
firmly pressing in the reset button (the appliance is delivered
with the safety pressure limiter disabled).
Push the temperature selector plug into the "set tempera-
ture" PCB.
Fit the appliance cover and secure with a screw.
Switch the mains power ON.
Calibrate the temperature. For this, turn the temperature se-
lector fully clockwise then fully anti-clockwise.
Check the function of the appliance.
Remove the protective foil from the control fascia.
Appliance handover
Explain the appliance function to users and familiarise them
with its operation.
Make users aware of potential dangers, especially the risk of
scalding.
Hand over these instructions.
11.2 Recommissioning
See chapter "Settings and displays / Following an interruption to
the water supply"
12. Shutting down the system
Isolate all poles of the appliance from the power supply.
Drain the appliance (see chapter "Maintenance").