Installation Guide
ASSEMBLY
Read carefully and understand assembly before beginning.
Do not fully tighten bolts until instructed to do so.
Page 2 / 3 
STEP 1
A: 1
D: 2
1: 2
Do not fully tighten any bolts until after Step 4 is complete.
STEP 2
B: 1
2: 4
3: 4
STEP 3
A: 1
1: 2
STEP 4
C: 1
2: 6
3: 6
•  Align Bottom Bar (D) with Side Panel (A). Loosely 
secure by hand-tighten M6x30mm Bolt (1).
•  Repeat to loosely fasten the remaining bottom bar to 
the opposite side.
•  With the ledge facing upward, and flush with the side panel, 
secure Bottom Panel (B) to the bottom bars using four 
M5x25mm Bolts (2) and four M5 Nuts (3).
•  Fasten remaining Side Panel (A) to the bottom bars by 
hand-tightening two M6x30mm Bolts (1).
•  Secure Back Panel (C) to the rear of the side panels using 
six M5x25mm Bolts (2) and six M5 Nuts (3).
Do not fully tighten any bolts until after Step 4 is complete.
Do not fully tighten any bolts until after Step 4 is complete.
06/2021
NOTE:
  Side Panels install 
with the tubular frame on the 
outside, screen on the inside.
LWT-B
Tighten all bolts after this step is complete.