Install Instructions

29 of 36 © 2016 Watts Water Technologies
Master Bathroom (normal heat loss, framed floor construction)
One zone, 120 volts: One cable. 35 ft. of CableStrap, or two 25-ft. rolls.
Vanity Vanity
Toilet
Bath Tub
Cable end
Install cables
at least 6” away
from toilet flange
CableStrap
Control Floor Sensor
1 spool 100 ft
2
3” spacing
counter open to floor
Master Bathroom
(normal heat loss, framed floor construction)
One zone, 120 volts: One cable. 49 ft. of CableStrap, or two 25-ft. rolls.
Floor
Sensor
Vanity
Install cables
at least 6” away
from toilet flange
Bath Tub
Toilet
Closet
Cable end
CableStrap
counter open
to floor
Control
1 spool
90 ft
2
3” spacing