User's Manual

SynapSense Intelligent Gateway Installation Guide
December 17, 2013
3
CHAPTER 2.
Getting Started
Before entering the facility to install and configure the Gateway devices, ensure the completion of the
following preparatory steps.
1. Review all warnings and precautions
.
2. Unpack Gateway kit(s) from boxes. Count and verify quantities. At least two Gateways are
required for redundancy.
3. Verify that one 110VAC or 220VAC power outlet is available within a few feet of each Gateway’s
intended installation location.
4. Verify that the data center operators have provided one static IP address and two open ports for
each Gateway to be installed (configuration uses port 80, data uses port 10001). Installation and
testing cannot begin without these address and port assignments.
5. Verify you have the latest SynapSense firmware and software, and applicable documentation.
6. Verify that the install team has all of the required tools and materials
.
Port 80 = Configuration via the Gateway’s web page.
Port 10001 = Data received from SynapSense wireless sensors.