VTR 100B LITE Installation and Service manual v2

Table Of Contents
10
| Installation
Fig. 8 Installation of mounting bracket without or with wooden blocks
2. Screw the mounting bracket (pos. 1) with the anti-vibration pad (pos. 2) to the wall (figure 8, pos. A). Screws are not
included, choose them based on your wall type. Use appropriate holes to screw the bracket firmly to the wall. Bottom
side of bracket should be 40 mm (H) below top of unit position.
Leave 15 mm gap between the mounting bracket and the cupboard for the cooker hood wires.
Note:
Make sure that the mounting bracket is completely horizontal once mounted on the wall. Check with a spirit
level.
In case the depth of cabinets is much greater than the unit, install wooden blocks (pos. W) to compensate the missing
distance (figure 8, pos. B). Then install the mounting bracket on the upper block. Choose thickness of blocks according
to your needs.
Thickness of wooden blocks should be 25–100 mm. If needed distance is lower than 25 mm, adjust bolts instead of us-
ing wooden blocks (see figure 20).
Caution
Be sure to select the appropriate type and length of the screws so that they could hold additional wood
blocks and the unit itself.
4.2.2 251-10/B cooker hood installation
Fig. 9 Installation of the cooker hood
Product name and number
251-10/B White Cookerhood 96698
251-10/B Stainless Cookerhood 96699
The cooker hood must be installed to the wall/cupboards
first before it can be mounted on the wall because the
cooker hood power supply and control cables at the back
must be led to the top and already mounted VTR 100/B
LITE unit will block access.