Topvex SoftCooler TR Installation instructions CE208767 A006

16
| Commissioning protocol
8 Commissioning protocol
Company:
Responsible:
8.1 General
Customer: Date:
Installation:
Object/unit:
Item no:
Installation address:
Model/size Serial no:
Designation:
8.2 Installation control
Moment Done Note
Control report cooling concerning installation established.
(Application shall in some cases be done, see chapter 3,
Refrigerant Control/Reporting).
All unit parts undamaged.
Installation carried out according to instructions (see
chapter 6.4.1, Assembly the Topvex SoftCooler and
chapter 6.5, Duct connections).
Condensation drain connected (see chapter 6.7,
Condensation drain).
Mains supply connected via the Safety switch (see chapter
6.8, Electrical connection).
By-pass damper connected when such is to be used,
accessory (see chapter 6.8.1, External/Internal
connections).
Internal operating cable connected (see chapter 6.8.1,
External/Internal connections).
The two transparent pressure measuring tubes to the
extract fan connected thru the Topvex SoftCooler
Supply and extract airflow adjusted
8.3 Preparing the control unit
To receive correct functions the following settings must be done in the control unit. Log in with service level using pass-
word 0612.
Moment Done Note
Select the menu Configuration > Functions >
Function activation > Heating/Cooling
sequence setup :
Choose Cooling
Set Type of cooler to DX
Set Type of feedback to Alarm
Select the menu Configuration > Functions >
Function activation > Heating/Cooling
sequence setup :
Choose Step controller 1
Set Step control sequence to Cooling
Set Number of steps to 2
Select the menu Configuration > Functions >
Function activation:
Check that Temperature control type is set as
Extract air cascade or Room cascade
208767 | A006