Topvex SoftCooler SR Installation instructions CE208765 A005

Commissioning protocol |
15
8 Commissioning protocol
Company:
Responsible:
8.1 General
Customer: Date:
Installation:
Object/unit:
Item no:
Installation address:
Model/size Serial no:
Designation:
8.2 Installation protocol
Moment Done Note
Control report cooling concerning installation established.
(Application shall in some cases be done, see chapter 3,
Refrigerant Control/Reporting).
All unit parts undamaged.
Installation carried out according to instructions (see
chapter 6.4.1, Assembly the Topvex SoftCooler.
Condensation drain connected (see chapter 6.6,
Condensation drain).
Mains supply connected via the Safety switch (see chapter
6.7, Electrical connection).
Internal operating cable connected (see chapter 6.7.1,
External/Internal connections).
Supply and extract airflow adjusted
8.3 Preparing control unit
To receive correct functions the following settings must be done in the control unit. Log in with service level using pass-
word 0612.
Moment Done Note
Select the menu Configuration > Functions >
Function activation > Heating/Cooling
sequence setup:
Choose Cooling
Set Type of cooler to DX
Set Type of feedback to Alarm
Select the menu Configuration > Functions >
Function activation > Heating/Cooling
sequence setup:
Choose Step controller 1
Set Step control sequence to Cooling
Set Number of steps to 1
Select the menu Configuration > Functions >
Function activation:
Check that Temperature control type is set as
Extract air cascade or Room cascade
Select the menu Configuration > Functions >
Temperature control:
Set Cooling recovery mode to Off
Select the menu Configuration > I/O allocation
settings > Digital outputs:
Set Signal for Step controller 1 step 1 to DO5
208765 | A005