IOM SYSHP MINI TANK

NOTE
During filling, it might not be possible to remove all air in the system. Remaining air will be removed through the automatic air
purge valve during the first operating hours of the system. Topping up the water afterwards might be required.
The water pressure indicated on the manometer will vary depending on the water temperature (higher pressure at higher
water temperature). However, at all times water pressure should remain above 0.5 bar to avoid air entering the circuit. The
unit might drain-off too much water through the pressure relief valve.
Water quality should be complied with EN 98/83 EC Directives.
Detailed water quality condition can be found in EN 98/83 EC Directives.
Connect the water supply to the filling valve and open the valve.
Make sure all the automatic air purge valves are open (at least 2 turns).
Filling with water until the manometer(field supply) indicates a pressure of approximately 2.0 bar. Remove air in the circuit as
much as possible using the automatic air purge valves.
Open the automatic air purge
valve, turn counterclockwise at
least 2 full turns to release air
from the system.
6.8 Filling water
6.8.1 Filling the water circuit
6.8.2 Filling the domestic hot water tank
1 Open every hot water tap in turn to purge air from the pipes of the system.
2 Open the cold water supply valve.
3 Close all water taps after all air is purged.
4 Check for water leakage.
5 Manually operate the field-installed pressure relief valve to ensure a free water flow through the discharge pipe.
NOTE
In most applications this minimum water volume will be satisfactory.
In critical processes or in rooms with a high heat load though, extra water might be required.
When circulation in each space heating loop is controlled by remotely controlled valves, it is important that this minimum
water volume is kept even if all the valves are closed.
if each space heating (cooling loop is controlled by the valves, the overpressure bypass valve(field supply) should be
mounted between the heating(cooling) loops.
Fig.6-8
17
Cold water inlet pressure should be less than 1.0MPa. Expansion vessel and safety valvefield supplyprotection pressure
is 1.0MPa
must be installed.
Warning and Water Quality Directive and Groundwater:This product is designed to comply with the European Water Quality
Directive 98/83/EC amended by 2015/1787/EU. The lifespan of the product is not guaranteed in the case of the use of
groundwater, such as spring water or well water, the use of tap water when salt or other impurities are contained, nor in
areas of acidic water quality. Maintenance and warranty costs related to these cases are the customer’s responsibility.
CAUTION