IOM SYSCROLL 20 35 AIR

16
4 - Installation
WARNING
Before filling the installation, remove any
impurity, such as sand, crushed stones and
welding scales, coating drops and any other
material which might damage the evaporator.
It is advisable to flush with disposable water bypassing the exchanger
to avoid clogging.
NOTE
The water used to fill the circuit shall be treated
in such as way that the pH will have the correct
value.
When two or several units are connected in parallel, to balance the
load losses of the various circuits, it is recommended to execute a
“reverse return” connection (see the diagram below).
UNIT 1
UNIT 2
Legend
S On/Off valves
VG Balancing valves
4.3 Water connections
The flow switch and the filter water, although not included in the
supply, must always be fitted such as plant components.
Their installation is mandatory for warranty.
WARNING
The attachments at the water inlet and outlet
shall be connected in compliance with the
instructions which can be found on the labels in
the proximity of the attachments.
Connect the water lines of the plants with the attachments of the unit
whose diameters and positions are shown in Chapter 9.
4.4 Water buffer tank
The accumulation tank is complete with all the hydraulic and electrical
components required for the correct operation of the system.
These systems are carefully assembled and tested at works. They
are ready for operation after having correctly realised all electrical
and hydraulic connections.
4.4.1 Features
The kit will include an Antifreeze Electric Heater, a drain valve, an
automatic filling unit and an automatic air vent.
No pump is arranged on the kit since it is mounted on the unit.
The tank is completely insulated with 30 Kg/m
3
closed cell
polyethylene in a silver colour and enclosed by a bearing structure
made of passivated and painted plates. The box is equipped with
bulkheads which can be easily opened for internal inspection.
The kit is installed beneath the chiller. It is an integral part of the unit
without changing the support area.
RECOMMENDED WATER COMPOSITION
PH 7,5 - 9
Electrical conductivity 10 - 500 μS/cm
Total hardness 4,5 - 8,5 dH
Temperature < 60 [°C]
Alkalinity (HCO
3
-
) 70-300 ppm
Alkalinity / Sulphates (HCO
3
-
/ SO
4
2-
) > 1 ppm
Sulphates (SO
4
2-
) < 70 ppm
Chlorides (Cl
-
) < 50 ppm
Free Chlorine < 0,5 ppm
Phosphates (PO
4
3-
) < 2 ppm
Ammonia (NH
3
) < 0,5 ppm
Ammonium Ion (NH
4
+
) < 2 ppm
Manganese Ion (Mn
2+
) < 0,05 ppm
Free Carbon Dioxide (CO
2
) < 5 ppm
Hydrogen Sufide (H
2
S) < 0,05 ppm
Oxygen Content < 0,1 ppm
Nitrates (NO
3
-
) < 100 ppm
Manganese (Mn) < 0,1 ppm
Iron (Fe) < 0,2 ppm
Aluminium (Al) < 0,2 ppm
Caution
If the water circuit is to be drained for a time exceeding one month, the
circuit must be fully charged with nitrogen to prevent any risk of corrosion
by differential venting