Commissioning GB
5 Commissioning
Danger
All electrical connections must be carried out by an authorized installer and in accordance with local rules
and regulations.
Before initial operation, check the following:
Electrical connection has been properly completed.
Protective earth has been connected.
Safety devices in place (protection grid).
Leftover installation materials and foreign materials have been removed from the casing.
Testing the installation:
Adjustment may be required in the electrical compartment during test (i.e. changing of the potentiometer), however
during operation the lid must be closed.
When putting into operation, check the following:
Connection data corresponds to the specifications on the nameplate: Maximum voltage +6%, -10%, according to IEC
38. Rated current must not be exceeded with more than 5% at rated voltage.
The direction of rotation should correspond to direction-of-rotation arrow (3 phase).
Smoothness of motor operation, (no abnormal noises).