1. Locate the Powerside Runway easily identied
by the Cylinder and Sheave roller mounting
structures welded on the underside. The
Powerside Runway will be positioned on the side
of the lift where the power units is installed.
3. Remove any pre-installed Cable sheaves
from the Powerside Runway making sure to pat
attention to the order in which they are removed
(This will help at the time of re-installation)
STEP 3
STEP 4
(Powerside Runway Installation)
(Oside Runway Installation)
Powerside Runway
Power Unit
Bracket
Flex Hose Hole
Utility Rail
Powerside
Runway
Bolt Powerside runway to the cross
tubes using four M12x100mm Hex
Head Bolts
Oside Runway
Position the Oside Runway on top of the
Cross Tubes with the Utility Rail located inside,
Determine the desired location of the Oside
Runway. align the holes in the Runway with
the desired holes on the cross tubes and bolt
together using four M12x100mm Hex Head Bolts
and Washers, Lubricate bolts with WD-40 or
equivalent and torque to rated ft/lbs.
4. Position the powerside Runway on top of the
cross Tube with the utility rail towards the center.
The Flex Tube Holes located at the side of the
pwerside Runway should be adjacent to power
unit column, Align the holes in the runway with the
holes on the Cross Tube and bolts together suing
four M12x100mm Hex Head Bolts and Washers,
Lubricate bolts with WD-40 or equivalent and
torque to rate ft/lbs.
SINGLE Cable Sheave
DOUBLE Cable Sheave
Bolt Powerside runway to the cross
tubes using four M12x100mm Hex
Head Bolts
Non-Powerside
Runway
Utility Rail
TORIN COMMERCIAL EQUIPMENT
27 REV 190425