Installation Steps
Step 1 Ensure the JBOX has been installed with a vertical single gang mud ring. See Figure 3.
Figure 3: Vertical Single Gang Mud Ring
Step 2 Turn off power at EcoSource or mounting location using a disconnect switch or breaker
lockout/tag out on appropriate breaker panel.
Step 3 Test that power is off by using a voltmeter.
Step 4 Strip the LINE wire back 0.25 inches.
Step 5 Cap the LINE wire with a wire nut or electrical tape.
Step 6 Cut the COMMON wire so the copper is flush with the insulation.
Step 7 Strip all wires except for COMMON back 0.25 inches.
Reminder: For all high voltage installations, a single gang mud ring must be mounted
VERTICALLY.
Step 8 Determine which end of the adapter plate should be installed as the top, and which end should
be installed as the bottom. As shown in Figure 4, the notch in the main display should be in the
upper left corner, and the smaller, vertical rectangle should be in the lower right corner.
Figure 4: Determine Top & Bottom of Plate
Step 9 Level the high voltage Telkonet JBOX adapter plate and mount to the mud ring with two #6-32
1” screws. See Figure 5.
EcoWave Featuring EcoTouch IO&M Guide Telkonet, Inc.
For Use with Firmware Version 2.x 20800 Swenson Drive, Suite 175
EcoSour ce Waukesha, WI 53186
Revision 2 (800) 380-9640