A. SEQUENCE OF OPERATIONS
50V61-143 CONTROL
ENERGIZED, INDUCER
ENERGIZED ON HIGH SPEED
THERMOSTAT CALLS FOR
HEAT W1 OR W1 & W2,
CONTACTS CLOSE
LOW FIRE PRESSURE
SWITCHES SENSES ADEQUATE
DIFFERENTIAL PRESSURE,
CONTACTS CLOSE
IV. STARTING THE UNIT
PREPURGE IGNITION DELAY,
INDUCER RUNS FOR 30 SECONDS
INDUCER REDUCES
TO LOW SPEED
LOW PRESSURE SWITCH
SENSES ADEQUATE
PRESSURE DIFFERENTIAL,
CONTACTS STAY CLOSED
POWER IS APPLIED TO
THE WHITE RODGERS 768A
SILICON NITRIDE IGNITOR.
IGNITOR WARM-UP IS
20 SECONDS