Operator's Manual

3. Use liquid soap to coat the hose barb of the
tee connections on both extension booms
( Figure 29 ). Install the boom extension hose
o v er the barb and secure it with a clamp .
Figure 29
1. Boom extension
6. Boom hose
2. Boom hose 7. Clamp
3. Clamp
8. Grommet
4. Tee connection 9. Tee connection
5. Center boom
4. Use liquid soap to coat the hose barb of the
center boom tee connection
5. R oute the center boom hose through the
g rommeted opening in the center boom
assembly . Connect the center boom supply
hose to the soaped barb and secure it with a
hose clamp
Step
13
Installing the Nozzles
No Parts Required
Procedure
T he nozzles y ou use to apply y our c hemicals v ar y
de pending on the rate of application that y ou need;
therefore , nozzles are not supplied with the kit. T o
obtain the cor rect nozzles for y our needs , contact
y our A uthorized T oro Distributor and be pre pared
to gi v e them then follo wing infor mation:
T he recommended application rate in US
g allons per acre , US g allons per 1000 sq ft, or
liters per hectare .
T he targ et speed or the v ehicle in miles per
hour or kilometers per hour .
T he nozzle spacing (typically 20 inc hes or 50
cm).
T o install a nozzle , complete the follo wing:
1. T hread or inser t the nozzle into the nozzle
rece ptacle follo w ed b y a g ask et.
2. Slide the nozzle rece ptacle o v er the nozzle
fitting on a tur ret.
3. T ur n the nozzle cloc kwise to loc k the cams on
the rece ptacle in place .
4. V erify the fan por tion of the nozzle .
See the Installation Instr uctions accompanying the
nozzles for more infor mation.
25