Instructions / Assembly

10/1/2012
3
STEP 1:
Check and Prepare Rough Opening for the installation of door unit.
Measure rough opening to confirm the rough opening
is the correct size.
The rough opening width must be 1 larger than the
overall door frame width, the rough opening height
must be ½” taller then the overall height of the complete
door frame including the threshold. (WARNING) A larger
than required rough opening will weaken the door
installation and may cause personal injury, property
damage or product failure.
The sill must be level and clean to install the door,
check the sub floor or slab foundation to make sure it is
level. DO NOT PROCEED to the next step until the
door unit can be installed onto a clean and level
surface. Scrape sand or fill the sub floor or slab
foundation with the appropriate material to insure a
clean and level sill.
Check all framing to and make sure that the frame
work is secure and will support the weight of the
iron/steel door unit.
Check the rough opening for plum and level using the
6 and 3 foot level. The rough opening must be plum and
level to install this door unit. Make any adjustments
needed to insure that the rough opening is plum and
level.
WARNING to avoid the potential for electrical shock
please make sure all electrical wiring next to the door
unit is installed to code and will not allow any exposed
electrical wire, to contact the door or frame.