HOW TO INSTALL DECKING
LOCATION AND INSTALLATION OF IRC-APPROVED POST MOUNTS CONCRETE
IMPORTANT NOTES:
» INSTALLATION SHOWN HERE IS FOR IRC
APPROVED APPLICATIONS ONLY.
» MAKE SURE CONCRETE IS LEVEL BEFORE INSTALLING POSTS.
» ALWAYS REFER TO YOUR LOCAL BUILDING CODE OFFICIAL
PRIOR TO INSTALLING ANY RAILING SYSTEM TO ENSURE ALL
CODE AND SAFETY REQUIREMENTS ARE MET. TREX CANNOT BE
HELD RESPONSIBLE FOR IMPROPER OR NON-RECOMMENDED
INSTALLATIONS.
»
CANNOT BE USED WITH TREX TRANSCEND COCKTAIL RAILING.
» See page 54
for sku information.
TOOLS NEEDED
»
Hammer
»
Drill and/or screw gun
»
3/8" (10 mm) drill bit for concrete
PARTS
» (1) Post mount
» (2) Guide blocks
» (18) #8-15 x 1-1/4" (32 mm)
Screws
» (2) 10 x 1" (25 mm)
Self-tapping screws
SKU ALPOSTHWCONC
(this SKU SOLD SEPARATELY)
» (4) 3/8" x 3-3/4"
(10 mm x 95 mm)
Expansion anchor
» (4) Flat washers
» (4) Hex nuts
Pre-drill Holes
1. Using post as a template, mark locations of the four
holes and drill into concrete at least 2-5/8" (66.7
mm) using a 3/8" (10 mm) masonry bit.
NOTE: You can either set drill bit to correct depth on
drill or mark drill bit with tape at required dimension to
ensure all holes are drilled at the correct depth.
2. Clean out holes to remove all concrete dust.
1
3/8"
(10 mm)
2