Pre-Installation Items
Recommended Clearances
The PRESTIGE Excellence is approved for
zero clearance to combustibles, excluding
vent and boiler piping.
- Boiler Piping - 1/4 inch from com-
bustible materials.
- Reference the appropriate vent supple-
ment for clearance requirements.
To provide serviceability to the unit it is
recommended that the following clear-
ances be maintained:
Top boiler jacket - 24 inches [610 mm].
Front - 24 inches [610 mm].
Bottom boiler piping - 24 inches [610 mm].
Rear - 0 inches
Sides - 6 inches [153 mm]
If the clearances listed above cannot be
maintained or the enclosure in which the
boiler is installed is less than 85 cubic feet,
the space must be ventilated. See page 6
for ventilation requirements.
When maintaining zero clearance or less
than recommended clearances, some
product labeling may become hidden
and unreadable.
When installing the PRESTIGE
Excellence in a confined space, sufficient
air must be provided for proper combus-
tion and venting and to allow, under
normal operating conditions, proper air
flow around the product to maintain
ambient temperatures within safe limits
to comply with the National Fuel Gas
Code NFPA 54 - latest edition.
Residential Garage Installations
When installing the PRESTIGE Excellence in a
residential garage, the following special precau-
tions per NFPA 54/ANSI Z223.1 must be taken:
- Mount the unit a minimum 18 inches
[458 mm] above the floor level of the
garage. Ensure the burner and ignition
devices / controls are no less than 18
inches [458 mm] above the floor level.
- Locate or protect the unit in a manner so it
cannot be damaged by a moving vehicle.
Boiler Freeze Protection Feature
The Trimax boiler management system has a
freeze protection feature built in. This feature
monitors the boiler temperature and responds as
follows when no call for heat is present:
- 46ºF [8ºC] CH (1) & Auxiliary Boiler
Pumps ON
- 42ºF [6ºC] CH (1), Auxiliary Boiler &
System Pumps ON, Burner operates at
low fire
- 60ºF [15ºC] Freeze protection ends.
Burner & all pumps OFF after complet-
ing CH Post Pump Time.
The boiler freeze protection feature is
disabled during a hard lockout, however
the circulators will operate.
The boiler freeze protection feature is
designed to protect the boiler. The boiler
should be installed in a primary/sec-
ondary piping arrangement if it is
installed in an unheated space or
exposed to water temperatures of 46ºF or
less. See Section IV for primary/sec-
ondary piping examples. See Section X
for antifreeze guides.
NOTICE
WARNING
WARNING
CAUTION
CAUTION
BEST PRACTICE