Installation Manual

Table Of Contents
Commissioning Procedures
4-8 © 1999 Triton Network Systems, Inc. All Rights Reserved.
CONFIDENTIAL & PROPRIETARY
D
O
N
O
T
C
O
P
Y
4 Move the IFU to the higher peak position as indicated by the multimeter
display.
5 Tighten the four vertical screws on the IFU mounting bracket.
6 Loosen the horizontal alignment nut on the IFU mounting bracket.
7 Sweep the IFU from the far left to the far right. The measured voltage of
the multimeter displays a succession of peak signals as the IFU moves.
Note the approximate position of the IFU when the higher peak occurs
and the corresponding voltage value.
8 Move the IFU to the higher peak position as indicated by the multimeter
display.
9 Tighten the horizontal alignment nut on the IFU mounting bracket.
10 Access the IFU Link Manager application and enable Power Control for
both the near-end and the far-end IFUs (see IFU Link Manager online
help).
11 Record the minimum, maximum, and actual RSSI levels set for the IFU in
Table A-4 and Table A-6.
12 Turn off the laptops, disconnect the test cables, and replace the protective
caps on the IFU test connectors.
13 Secure all IFU cabling with UV-rated tie-wraps. Continue to tie wrap the
cables every 18 inches until they enter the building.