3 Connect the SmartBits test set from 100BaseFX port 4 to IFU Beta
100BaseFX Payload port on the patch panel with the MT-RJ to SC fiber
adapters.
4 Turn on power to the SmartBits test set.
5 On the laptop, open the SmartApplication program.
6 Select File>Open and then click Building Payload Test (file provided by
Triton Network Systems).
7 Select Run then click Packet Loss to run the Packet Loss tests.
8 Record the results of 64, 76, 128, 164, 512, 1024, and 1518 byte packet
tests in Fast Ethernet Payload Test on page A-4.
9 Stop all tests, disconnect the test equipment, and return the equipment to
its previous state.
Repeat this procedure for each IFU site.