Installation Guide
11
FP9K-DX-XLT
Jan 2019
16. Begin cable routing installation to Column Top Caps by first ensuring the pre-installed steel
Cables are properly routed around each Cable Sheave and are not in a bind. Note: if
Cable(s) comes off the Cable Sheave, it will be required to remove the Cable Sheave
assembly to reinstall the Cable, due to welded cable guide brackets.
17. Pull the slack for each Cable from the corner ends of the Mainside Runway and route the
appropriate Cable(s) to each Column Top Caps, while ensuring that the Plastic Cable Pulley
(#95) is between the Cable and the Lock Ladder as shown in Fig.7. This will allow the
secondary Slack Cable Lock to function properly. See Fig.7 below for Cable routing
installation.
Fig. 7
Plastic Cable
Pulley
Nylon Lock Nut
& Washer