Installation Guide

Issued/Revised:
08/30/13
UP171F ELLIPTICAL (FOOTING)
FitTech
800.458.5872
www.actionfitoutdoors.com 2
ActionFit
UP171I ELLIPTICAL (IN GROUND)
UP171S ELLIPTICAL (SURFACE)
NOTE: Do not overtighten bolts. To overtighten may cause buckling or dimpling of some parts.
NOTE: Read installation instructions thoroughly before starting assembly. Pour concrete only after final assembly is completed.
Bracing material is required during assembly.
NOTE: Assembly and leveling times will be greatly reduced if a transit is used to set location and depth of ground holes.
INSTALLATION INSTRUCTIONS FOR UP171F (FOOTING):
1. Dig holes or drill holes according to Plan View and Elevation View. NOTE: Due to extremes in weather and soil conditions, hole
size may have to be increased to meet local conditions.
2. Fill hole with concrete. While the concrete is still soft, yet firm enough to support the Elliptical, Place (4) Anchor Bolts of the
Elliptical in postion. See Footing Detail. NOTE: Use Elliptical as a template for Anchor Bolt location, then remove Elliptical.
IMPORTANT:
DO NOT MOUNT THE ELLIPTICAL TO THE ANCHOR BOLTS FOR AT LEAST 7 DAYS.
3. After concrete has cured and set for a minimum of 7 Days, attach Elliptical to 3/4" Anchor Bolt using 3/4" Flat Washer (2" O.D.),
3/4" Lock Washer, and 3/4" Hex Nut. See Footing Assembly Detail.
4. Attach Base Cover to Equipment Post using Base Cover Nut and Base Cover Bolt included with Base Cover. See Base Cover
Detail.
INSTALLATION INSTRUCTIONS FOR UP171I (IN-GROUND):
1. Dig holes or drill holes according to Plan View and Elevation View. NOTE: Due to extremes in weather and soil conditions, hole
size may have to be increased to meet local conditions.
2. Attach the Footbuck Weld Assembly to the Elliptical using 3/4" Hex Nut, 3/4" Lockwasher, 3/4" Flatwasher (2" O.D.),
3/4" x 2" Hex Head Cap Screw. See In-Ground Assembly Detail.
3. Place Elliptical into hole making sure it rests on the brick. See In-Ground Detail.
4. Level Elliptical using sway bracing.
5. Pour concrete according to the Plan View and Elevation View. Allow concrete to cure for a minimum of 7 days.
6. Attach Base Cover to Equipment Post using Base Cover Detail.
INSTALLATION INSTRUCTIONS FOR UP171S (SURFACE):
1. Mark correct location of holes for Wedge Anchor using the Base Plate as a guide.
2. Drill 3/4" x 2 1/2" hole in concrete for Wedge Anchor. See Surface Detail.
3. Insert Wedge Anchors and secure with 3/4" Flatwasher (2" O.D.), 3/4" Lockwasher, and 3/4" Hex Nut. See Surface Assembly
Detail.
4. Attach Base Cover to Equipment Post using Base Cover Detail.