12.4 Controller Section Operation and Settings. At this point, before the final
installation connections, read sections 13 through 21, covering the Control Panel
operation. Next, go back to sections 19, 20 and 21 and make the signal connec-
tions, controller adjustments, temperature compensation adjustment and alarm
enabling settings.
WARNING: Remember to take precautions each time the system is turned
on and also when connecting or disconnecting the battery. Remember that
the battery has a hazardous voltage at its terminals. Also remember to
allow 5 minutes for internal capacitors to discharge after disconnecting
the AC input power and the battery.
12.5 Connection to Loads. With input AC power unplugged, the battery disconnected
and no other power sources connected to the loads, make sure that all load
circuit breakers are set to the OFF position and/or all GMT fuses are removed.
See Figures 2 and 4. Connect load wires to each set of output terminals, one at a
time. Note that the front panel breaker and fuse numbers directly correspond to
the output terminal numbers. Be sure to connect the polarities correctly as
shown in Figure 4.
12.6 Connection to Battery. With AC input unplugged, remove the three rectifier
modules from the system chassis. Make sure all load circuit breakers are in the
OFF position and/or all GMT fuses removed. Set the battery circuit breaker to the
OFF position. Carefully connect the battery cables to the DIN-Rail battery termi-
nals shown in Figure 2. while observing the correct polarity.
WARNING: Improper polarity of the battery connection may damage the
power system. Take precautions when installing the battery and note that
the battery cables are “hot” (live).
Set the battery circuit breaker to the ON position and observe the reading on the
digital voltmeter on the controller panel or connected to the test points. It
should indicate the voltage of the battery, approximately 48, 24, and 12VDC
when charged. If the battery is connected with wrong polarity, there will be no
reading on the test points.