User's Manual

Chapter 3 Installation
3.15.2 Terminating a WR3 40 Flange Output
The following steps sho
uld be performed to terminate a WR 340 flange output:
1. Place the rubber ring in the WR 340 flange groove – see Figure 3-39
.
2. Connect the transmission line to the WR 340 flange according to site drawings.
3. Secure the transmission line in place by installing a 1/4-20x1” hex head bolt with
1/4” flat washer and 1/4” spring washer in each one of the holes (3 total) – see
Figure 3-39
. A 7/16 torque wrench with a rating of 61.5 In. Lbs. should be used to
tighten the bolt.
Figure 3-39 WR 340 Flange Connection (before and after)
Picture TBD
1) Rubber Ring
2) 1/4-20x1” Hex Head Bolt with 1/4” Flat Washer and 1/4” Lock Washer
3.15.3 Terminating a 7/8” EIA Flange Output
The fol
lowing steps should be performed to terminate a 7/8” EIA flange output:
1. Insert the inner connector into the 7/8” EIA flange – see Figure 3-40
.
2. Place the rubber ring in the 7/8” EIA flange groove – see Figure 3-40
.
3. Connect the transmission line to the 7/8” EIA flange according to site drawings.
4. Secure the transmission line in place by installing a 1/4-20x1” hex head bolt with
1/4” flat washer and 1/4” spring washer in each one of the holes (3 total) – see
Figure 3-39
. A 7/16 torque wrench with a rating of 61.5 In. Lbs. should be used to
tighten the bolt.
SX03-2000
0-01-M01 3-45