Technical data

Manual - Solar hot water systems48
Wiring plan 5
- Boiler from third party manufacturer
- Wiring via standard wiring box
- Solar circuit control via VRS 560
- Solar cylinder reheating control via a separate hot
water programmer from a third party manufacturer
- Heating circuit control via a separate central heating
programmer from a third party manufacturer
- Overview of the connection of the cylinder thermostat
to the wiring box.
- Installation of two VR 10 temperature sensors in the
solar cylinder (see Fig. 5.35)
- Attachment of the solar gain sensor to the solar
circuit return (see Fig. 5.35)
- Connection of the solar pump to the solar control via
its own thermal cut out (see Fig. 5.36)
Fit a wiring box near to the cylinder for easy electrical
connection.
2
3
Fig. 5.35 Installation of the VR 10 temperature sensor
Push one of the VR 10 temperature sensors (1)
supplied with the solar control in an immersion sleeve
where there is still room, as illustrated in Fig. 5.36.
Connect this temperature sensor to terminal “SP 1” in
the auroMATIC 560 solar control.
Push a VR 10 temperature sensor (3) in the immersion
sleeve for the bottom cylinder area.
Connect this temperature sensor to terminal “SP 2” in
the auroMATIC 560 solar control.
Attach the temperature sensor for the gain (2) to the
return pipe of the solar circuit nearby the solar
cylinder.
Connect this temperature sensor to the terminal
“Ertrag” in the auroMATIC 560 solar control.
Make sure the temperature sensors of the immersion
heater, solar cylinder and solar control fit properly in
the immersion sleeves.
h
Note!
Set the controller of the cylinder thermostat to
target temperature (1, Fig. 5.20).
Set the maximum temperature (MAXT 1) of the
auroMATIC 560 solar control to 70 ºC
(see auroMATIC 560 manual).
Connect the collector temperature sensor to terminal
“Kol 1” in the auroMATIC 560 solar control.
1
3
A
B
C
D
A
B
C
D
3
3
Fig. 5.36 Connection diagram of the solar pump TCO
Connect the solar pump, the thermal cut out intended
for this purpose and terminal “Kol 1-P” of the solar
control to each other by means of an additionally
protected terminal strip.
Wire up the boiler of the third-party manufacturer, the
programmer and the room thermostat.
Establish the connections to the mains supply.
5 Installation