3.3.2. Performing Resistance, Excitation, and Ratio Tests
The following procedure describes the general steps for performing excitation, resistance, and
ratio tests.
a. When the EZCT-2000A is turned on, it will first go through a start-up cycle and load the
firmware. Then the “START-UP” menu will be displayed as shown below:
Press the [1] key (RUN TEST) to start a test.
b. The following screen will be displayed:
Select the test type by pressing the corresponding key ([1] - [5])
c. The following screen will be displayed:
Select the tap connection by pressing the corresponding key (
[1] - [4]). If the tap
connection is not listed, press the [5] key to view the next page of options.
d. If the selected test included an excitation test, the following screen will be displayed:
Select a test voltage range by pressing the corresponding key (
[1] - [5]).
SELECT VOLTAGE RANGE:
1. 50V
2. 300V
3. 500V
4. 1200V
5. 2000V
SELECT TAP:
1. X1-X2
2. X1-X3
3. X1-X4
4. X1-X5
5. NEXT PAGE
1. Res, excit & ratio
2. excitation & ratio
3. excitation only
4. ratio only
5. resistance & excit
1. RUN TEST 02/14/10
2. SETUP 10:24:25
3. TEST PLANS
4. DIAGNOSTIC