Specifications
RDNO ATHLETIC PARK
AMENITIES BUILDINGS
WE File No.029042.00
May 30, 2014
7 | P a g e
13.2 Paint all pipe hangers and exposed sleeves, in exposed areas, with a rust inhibiting primer,
as they are installed.
13.3 Repaint all marred factory finished equipment supplied under Division 15, to match the
original factory finish.
14 PENETRATION OF FIRE SEPARATIONS
14.1 Seal all pipe and duct penetrations through fire separations with "3M Fire Barrier" system
or equal U.L. Listed system.
15 TEMPORARY USE OF MECHANICAL SYSTEMS
15.1 Obtain written permission from the Consultant if it is desired to use the mechanical
systems for temporary heat.
15.2 The following conditions must be confirmed prior to the use of the mechanical systems for
temporary heating.
.1 Any equipment start-ups shall comply with specified procedures.
.2 All sanding must be complete, spray painting must be complete.
.3 The contractor must pay for the gas/electricity.
.4 All inspectors approvals must be received.
.5 Lubricate all equipment operated.
.6 Alarms/controls must be operational.
15.3 During the temporary heating period, comply with the following conditions:
.1 Keep all rooms broom clean.
.2 Maintain chemical treatment of piping systems.
.3 Maintain the systems.
.4 Operate the units utilizing 100% outside air if possible to avoid pulling building air
into the return ducts and the units.
15.4 Before handing the systems over to the Owner, comply with the following conditions:
.1 Bring plant to” as-new” conditions.
.2 Replace all panel type air filters installed under this contract with new filters.
.3 Re clean ductwork as necessary and provide a report from the approved duct
cleaning agency certifying that the ductwork is clean.
16 SYSTEMS COMMISSIONING, VERIFICATION AND DEMONSTRATION
16.1 Be responsible for the performance and commissioning of all equipment provided under
Division 15. Commissioning is the process of advancing the installation from the stage of
static completion to full working order to specified requirements. It is the activation of the
completed installation.
16.2 Acceptable Commissioning Contractors: BC Tech Engineering Services, R.A. Bruce
Associates, Inland Technical Services, MDT Systems, Western Mechanical Services, KD
Engineering.
16.3 In consultation with the General Contractor, ensure that sufficient time is allowed and fully
identified on the construction schedule for the proper commissioning of all mechanical
systems.
16.4 Commissioning is concluded when mechanical systems have been balanced and the
installation is in full working order and acceptable for use. The work will include the
following: