.4 Pumps, fans, heaters, unit heaters and coils.
.5 Sprinkler fire protection systems.
.6 Sewage and septic installations.
.7 Tanks - domestic hot water and expansion.
.3 After demonstration obtain the Owner's signature certifying that the demonstration
has been performed and completed to their satisfaction.
17 SUBSTANTIAL PERFORMANCE REQUIREMENTS
17.1 Before the Consultant is requested to make an inspection for Substantial Performance of
the work:
.1 Commission all systems and prove out all components, interlocks and safety
devices.
.2 Submit a letter certifying that all work (including calibration of instruments and
balancing of systems) is complete, operational, clean and all required submissions
have been completed.
17.2 The work will not be considered to be ready for use or substantially complete until the
following requirements have been met:
.1 All life safety items are completed and fully functional.
.2 All reported deficiencies have been corrected.
.3 Testing and balancing completed.
.4 Operating and Maintenance Manuals completed.
.5 "As Built" Record Drawing ready for review.
.6 System Commissioning has been completed and has been verified by Consultant.
.7 All demonstrations to the Owner have been completed.
18 OPERATING & MAINTENANCE MANUALS
18.1 Prepare instruction manuals which include equipment manufacturers' operating and
maintenance bulletins, a report on the balancing of the air and water systems and a report
on chlorination of water mains. The manuals shall be prepared by the Commissioning
Contractor.
18.2 The manufacturers' bulletins shall include:
.1 General description of the equipment and their operation.
.2 Normal maintenance and minor trouble-shooting of each major item.
.3 Wiring diagrams.
.4 Control diagrams.
.5 Spare parts list.
.6 Local source of supply.
18.3 Submit three copies in suitably labeled hard cover binders, to the Consultant at least ten
days prior to the Substantial Performance inspection date.
18.4 Provide a CD-ROM based copy of the Operating & Maintenance Manuals described
above.
.1 The CD-Rom shall consist of all data in the manuals, arranged in a “pdf” format file,
with an interactive menu system of bookmarks to match the manual format.
.2 Include the latest version of Adobe Acrobat Reader.
.3 Include “pdf” format copies of the as-built project drawings (contact the consultant
for files).