Specifications

RDNO ATHLETIC PARK
AMENITIES BUILDINGS
WE File No.029042.00
May 30, 2014
5 | P a g e
.2 Balancing of the air and water systems. Make provisions for easy access for air and
water balancer.
.3 Revision and testing of the heating, ventilation, plumbing and sprinkler systems in
the area.
.4 Disposal of all unused material.
.5 Be responsible for the performance and commissioning of all equipment supplied
and installed for the project (including all equipment supplied by the Owner where
applicable).
3 STANDARD OF ACCEPTANCE
3.1 Means that item named and specified by manufacturer and/or catalogue number forms part
of specification and sets standard regarding performance, quality of material and
workmanship and when used in conjunction with a referenced standard, shall be deemed
to supplement the standard.
3.2 Where two or more manufacturers are listed, the manufacturer's name shown underlined
or shown with a model name and/or number, was used in preparing the design. Tenders
may be based on any one of those named, provided that they meet every aspect of the
drawings and specifications.
3.3 Where other than the underlined manufacturer or named manufacturer is selected or
approved, include for the cost of any resulting work (both under this Division and other
Divisions) and any necessary redesign of installation or structure. Submit redesign
drawings for review with Shop Drawings. Maintain installation, access and servicing
clearances. Redesign drawings shall be to scale and of a standard equal to the Project
Drawings.
3.4 Where two or more items of equipment and/or material, of the same type, are required,
provide products of a single manufacturer.
3.5 A visible manufacturer's nameplate shall indicate manufacturer's name, model number,
serial number, capacity data, electrical characteristics and approval stamps.
4 ADDITION OF ACCEPTABLE MANUFACTURERS
4.1 Material/products considered to satisfy the specification, but of a manufacturer other than
those named in the Specification may be submitted to the Consultant for consideration not
later than five (5) working days prior to closing of tender
4.2 Addition of manufacturer's names to the specifications will be in writing by the Consultant.
5 EXISTING SERVICES
5.1 Confirm locations and routings of all existing services which might be affected by the work.
Protect existing and repair any damage occasioned by the work. Accommodate work
changes in location and routing as may be necessary.
6 CUTTING & PATCHING
6.1 Be responsible for all cutting, patching, digging, canning and coring required to
accommodate the mechanical services. Make good all revisions to match the original
condition.