Specifications

RDNO ATHLETIC PARK
AMENITIES BUILDINGS
WE File No.029042.00
May 30, 2014
6 | P a g e
6.2 Verify the location of existing service runs and structural reinforcement within existing roof,
floors and walls prior to cutting. Cutting of structural building components shall only take
place upon the receipt of specific written approval of the Structural Consultant. Repairs to
existing services damaged as a result of cutting is included in this section of the work.
7 MISCELLANEOUS METAL
7.1 Be responsible for all miscellaneous steel work relative to the Specifications, including but
not limited to support of equipment.
7.2 All steel work shall be prime coated, ready for paint finish.
8 ACCESSIBILITY
8.1 Install all work so as to be readily accessible for adjustment, inspection, operation and
maintenance.
9 ACCESS DOORS
9.1 Install at all concealed dampers, traps, unions, valves, water hammer arrestors, special
equipment, and trap primers.
9.2 Locate access doors so that all concealed items are readily accessible for adjustment,
operation and maintenance.
9.3 Do not locate access doors in feature wall or ceiling construction without the prior approval
of the consultant. Locate in service areas wherever possible.
10 GUARDS AND COVERS
10.1 Provide removable protective guards on all exposed V-belt drives and shaft couplings in
accordance with Worker's Compensation Board requirements.
10.2 Removable access covers shall be provided for all equipment installed under this project.
11 LUBRICATION OF EQUIPMENT
11.1 Lubricate all equipment prior to being operated, except sealed bearings, which shall be
checked.
11.2 Use the lubricant recommended by the manufacturer for the service for which the
equipment is specified.
12 ESCUTCHEONS
12.1 Provide escutcheons on all pipes passing through finished walls, floors and ceilings.
12.2 Escutcheons shall be chrome plated or stainless steel suitable for dimensions of piping and
insulation.
13 PAINTING
13.1 Clean exposed bare metal surfaces supplied under Division 15 removing all dirt, dust,
grease and millscale. Apply at least one coat of corrosion resistant primer paint to all
supports and equipment fabricated from ferrous metal. Paint all exposed ducts, equipment
and supports with two finishing coats of paint; color to be as directed by the Owner.